Government Services Mobile App — New Release
Add to watchlistThe new release of the government services app: the most-used services, request tracking, notifications and bank e-payment.
Budget (BAC)
Actual cost
62% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure23 December 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-01-21 | 2026-03-07 | +45 days | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-04-15 | 2026-07-02 | +78 days | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-08-17 | 2026-11-11 | +86 days | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-09 | 2026-12-19 | +40 days | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-01-31 | 2027-01-31 | On time | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
64%Awaiting acceptance
10%Not handed in
26%Deliverable flow
Display options
| Project plan & baseline015-D1 | 5% | CRT-015-01 | Approved | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Basel Al-Mahayni | 2025-12-11 | V1 | 3 of 3 |
| Monitoring & reporting015-D2 | 5% | CRT-015-02 | Approved | Basel Al-MahayniBasel Al-MahayniDirector General, Digital Government Services & Portfolio Manager, Digital Government Services & DataP-003basel.almahayni@psa.gov.sy | Basel Al-Mahayni | 2026-01-21 | V1 | 3 of 3 |
| Business requirements015-D3 | 11% | CRT-015-03 | Approved | Basel Al-MahayniBasel Al-MahayniDirector General, Digital Government Services & Portfolio Manager, Digital Government Services & DataP-003basel.almahayni@psa.gov.sy | Basel Al-Mahayni | 2026-03-04 | V1 | 3 of 3 |
| Solution design015-D4 | 11% | CRT-015-04 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Basel Al-Mahayni | 2026-04-15 | V1 | 3 of 3 |
| Release 1015-D5 | 16% | CRT-015-05 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Basel Al-Mahayni | 2026-05-26 | V1 | 3 of 3 |
| Release 2015-D6 | 16% | CRT-015-06 | Approved | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Basel Al-Mahayni | 2026-07-07 | V1 | 3 of 3 |
| Integrations015-D7 | 10% | — | Under review | Basel Al-MahayniBasel Al-MahayniDirector General, Digital Government Services & Portfolio Manager, Digital Government Services & DataP-003basel.almahayni@psa.gov.sy | Basel Al-Mahayni | 2026-08-17 | V1 | 1 of 3 |
| System testing015-D8 | 7% | — | Draft | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Basel Al-Mahayni | 2026-09-28 | V0 | 0 of 3 |
| User acceptance testing015-D9 | 7% | — | Draft | Basel Al-MahayniBasel Al-MahayniDirector General, Digital Government Services & Portfolio Manager, Digital Government Services & DataP-003basel.almahayni@psa.gov.sy | Basel Al-Mahayni | 2026-11-09 | V0 | 0 of 3 |
| Training & change015-D10 | 6% | — | Draft | Basel Al-MahayniBasel Al-MahayniDirector General, Digital Government Services & Portfolio Manager, Digital Government Services & DataP-003basel.almahayni@psa.gov.sy | Basel Al-Mahayni | 2026-12-20 | V0 | 0 of 3 |
| Go-live & handover015-D11 | 6% | — | Draft | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Basel Al-Mahayni | 2027-01-31 | V0 | 0 of 3 |
| Total · 11 | 100% |