PRJ-2026-015On track4ExecutionScrumIn progressDelivered by:Ministry of Communications and Information Technology

Government Services Mobile App — New Release

Add to watchlist

The new release of the government services app: the most-used services, request tracking, notifications and bank e-payment.

Budget (BAC)

SYP 315M

Actual cost

SYP 193.8M

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 302.9M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
PSA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2025-10-30⁩
ApprovedPRJ-2026-015Government Services Mobile App — New Release

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-015
Project
Government Services Mobile App — New Release
Portfolio
Digital Government Services & Data Portfolio
Sector
Local Development & Governorates Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Kinan Azzam

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-10-05⁩

Baseline finish

⁦2027-01-31⁩

Forecast finish

⁦2027-01-28⁩

SPI

1.02

MilestonePlannedForecastSlip
Project plan approved⁦2026-01-21⁩⁦2026-03-07⁩+45 days
Designs approved⁦2026-04-15⁩⁦2026-07-02⁩+78 days
Build complete⁦2026-08-17⁩⁦2026-11-11⁩+86 days
Testing & acceptance complete⁦2026-11-09⁩⁦2026-12-19⁩+40 days
Final handover⁦2027-01-31⁩⁦2027-01-31⁩0

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦5%⁩⁦2025-12-11⁩Kinan Azzam
Monitoring & reporting⁦5%⁩⁦2026-01-21⁩Basel Al-Mahayni
Business requirements⁦11%⁩⁦2026-03-04⁩Basel Al-Mahayni
Solution design⁦11%⁩⁦2026-04-15⁩Eng. Khaled Al-Kayyali
Release 1⁦16%⁩⁦2026-05-26⁩Eng. Khaled Al-Kayyali
Release 2⁦16%⁩⁦2026-07-07⁩Kinan Azzam
Integrations⁦10%⁩⁦2026-08-17⁩Basel Al-Mahayni
System testing⁦7%⁩⁦2026-09-28⁩Kinan Azzam
User acceptance testing⁦7%⁩⁦2026-11-09⁩Basel Al-Mahayni
Training & change⁦6%⁩⁦2026-12-20⁩Basel Al-Mahayni
Go-live & handover⁦6%⁩⁦2027-01-31⁩Eng. Khaled Al-Kayyali
Accepted with a certificate⁦64%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
No risks recorded

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyKinan Azzam
Project ownerDeliverable status and acceptance datesFortnightlyKinan Azzam
PMOData and indicator updatesWeeklyKinan Azzam
BeneficiariesWhat changes and whenAt each milestoneKinan Azzam
Team memberRoleAllocation
Kinan AzzamProject manager⁦40%⁩
Eng. Lina Al-AttarProgramme oversight, mobile app⁦15%⁩
Ibrahim Al-SaeedProject owner⁦5%⁩
Joud HammamiApp testing⁦40%⁩
Hamza Al-HusseinApp APIs to the unified platform⁦35%⁩
Hiba Al-ShamiApp service requirements⁦25%⁩
—App-to-unified platform integration⁦60%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Kinan AzzamSenior Digital Delivery Consultant — National PMOSubmitted—⁦2025-10-30⁩ 10:01
2Methodology review — PMOMethodology reviewMariam Al-ZoubiPMO — analystApprovedComplete against the project management plan template.⁦2025-11-02⁩ 12:03
3Technical acceptance — project ownerTechnical acceptanceBasel Al-MahayniProject ownerApproved—⁦2025-11-04⁩ 13:10
4Cash flow & financial commitmentFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-11-05⁩ 11:56
5Plan aligned with the contractsFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2025-11-09⁩ 12:33
6Sponsor approvalTechnical acceptanceEng. Khaled Al-KayyaliProject sponsorApproved—⁦2025-11-11⁩ 10:31

Signatures

Methodology review — PMO

Mariam Al-Zoubi

Approved⁦2025-11-02⁩

Technical acceptance — project owner

Basel Al-Mahayni

Approved⁦2025-11-04⁩

Cash flow & financial commitment

Rasha Al-Mudarres

Approved⁦2025-11-05⁩

Plan aligned with the contracts

Abdullah Al-Ujaili

Approved⁦2025-11-09⁩

Sponsor approval

Eng. Khaled Al-Kayyali

Approved⁦2025-11-11⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Kinan Azzam on ⁦2025-10-30⁩

  1. Methodology review

    Methodology review — PMO

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-11-02⁩ at ⁦12:03⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Basel Al-Mahayni · Project owner

    Approved · ⁦2025-11-04⁩ at ⁦13:10⁩

  3. Financial approval

    Cash flow & financial commitment

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-11-05⁩ at ⁦11:56⁩

  4. Financial approval

    Plan aligned with the contracts

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-11-09⁩ at ⁦12:33⁩

  5. Technical acceptance

    Sponsor approval

    Eng. Khaled Al-Kayyali · Project sponsor

    Approved · ⁦2025-11-11⁩ at ⁦10:31⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-10-30⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Kinan Azzam

  2. V1Returned for edit⁦2025-10-16⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Kinan Azzam

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close