PRJ-2026-023On track2InitiationAgileNot startedDelivered by:Planning and Statistics Authority

Medium-Term Plan Implementation Tracker (ministries & governorates)

Add to watchlist

A system that follows each ministry’s and governorate’s delivery of the 2026–2028 medium-term plan and the steering committee’s recommendations, with progress indicators and delay alerts.

Budget (BAC)

SYP 700M

Actual cost

SYP 7M

⁦1%⁩ of budget

Progress

⁦1%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 700M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

InitiationStage ⁦2⁩ of ⁦5⁩

Next gate:Planning6 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current stageInitiation · Current stage
  3. Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
  4. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+6

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦1% done against 1% planned⁩.

⁦SPI 1⁩.⁦00⁩, ⁦CPI 1⁩.⁦00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Balanced Local Development across the GovernoratesSO-6.2Governorate plans and a balanced share of public investment

Main initiative

SI-6.2.1National indicators & plan follow-up

Contribution to the initiative⁦57%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

Annual work-plan line
WP-2026-023
Classification
External

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦1%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦99%⁩

1 deliverable accepted

  • Project plan & baseline⁦1%⁩

0 deliverables under inspection or acceptance

    Progress & earned value

    ⁦1⁩ of ⁦5⁩ milestones complete

    Earned-value curve

    Planned, earned and actual to the data date, cumulative, with the forecast cost tail

    • Planned value
    • Earned value
    • Actual cost
    • Estimate at completion
    • Budget at completion

    Budget & commitments

    Commitments are ⁦2%⁩ of budget

    SYP7M/ SYP700M
    Actual spend
    SYP7M
    Committed
    SYP15M
    Approved budget
    SYP700M
    Estimate at completion
    SYP700M

    Next milestones

    • Contract signed⁦2026-11-22⁩On track
    • 50% of works complete⁦2027-05-10⁩On track
    • Provisional acceptance⁦2027-11-23⁩On track
    • Closure⁦2027-12-31⁩On track

    Waiting on someone

    ⁦2⁩ approvals and ⁦1⁩ open action on this project

    Approvals & requests

    From «My actions» for this project

    Actions

    ⁦1⁩ open

    • Review the conditions on the plan tracker gateRazan Al-RifaiIn 29 days2026-11-26Medium

    Change requests

    Cost and schedule impact

    • No change requests

    Risks & impediments

    0 open risks, exposure SYP 0

    Risk map

    Probability
    5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
    4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
    3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
    2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
    1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
    12345

    Impact

    • Critical0
    • High0
    • Medium0
    • Low0

    Top risks

    • No open risks

    Open impediments

    ⁦0⁩ escalated

    • No open impediments

    Deliverables

    ⁦1⁩ of ⁦11⁩ approved

    • Project plan & baseline023-D1 · V1 · CRT-023-01⁦1%⁩Razan Al-Rifai2026-11-112026-11-11Approved
    • Monitoring & reporting023-D2 · V0⁦4%⁩Iman Al-JasemIn 56 days2026-12-23Draft
    • Business requirements023-D3 · V0⁦9%⁩Iman Al-JasemIn 97 days2027-02-02Draft
    • Solution design023-D4 · V0⁦9%⁩Eng. Mustafa Al-AwaIn 139 days2027-03-16Draft
    • Release 1023-D5 · V0⁦14%⁩Eng. Mustafa Al-AwaIn 180 days2027-04-26Draft
    • Release 2023-D6 · V0⁦14%⁩Razan Al-RifaiIn 222 days2027-06-07Draft
    • Integrations023-D7 · V0⁦14%⁩Iman Al-JasemIn 263 days2027-07-18Draft
    • System testing023-D8 · V0⁦10%⁩Razan Al-RifaiIn 305 days2027-08-29Draft
    • User acceptance testing023-D9 · V0⁦10%⁩Iman Al-JasemIn 346 days2027-10-09Draft
    • Training & change023-D10 · V0⁦8%⁩Iman Al-JasemIn 388 days2027-11-20Draft
    • Go-live & handover023-D11 · V0⁦7%⁩Eng. Mustafa Al-AwaIn 429 days2027-12-31Draft

    Team, contracts & documents

    Team

    2 members

    Razan Al-Rifai · Director, Data & AIBasel Al-Mahayni · Director General, Digital Government Services & Portfolio Manager, Digital Government Services & Data
    • Razan Al-RifaiRazan Al-RifaiDirector, Data & AIProject managerP-027razan.alrifai@psa.gov.sy⁦35%⁩
    • Basel Al-MahayniBasel Al-MahayniDirector General, Digital Government Services & Portfolio Manager, Digital Government Services & DataDigital-services lead, plan implementation trackerP-003basel.almahayni@psa.gov.sy⁦15%⁩

    Contracts

    0 contracts

    • No external contracts — delivered in-house