Medium-Term Plan Implementation Tracker (ministries & governorates)
Add to watchlistA system that follows each ministry’s and governorate’s delivery of the 2026–2028 medium-term plan and the steering committee’s recommendations, with progress indicators and delay alerts.
Budget (BAC)
Actual cost
1% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
InitiationStage 2 of 5
Next gate:Planning6 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current stageInitiation · Current stage
- Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-12-23 | 2027-01-24 | +32 days | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-03-16 | 2027-04-10 | +25 days | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-07-18 | 2027-08-02 | +15 days | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | On track | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-10-09 | 2027-10-17 | +8 days | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | On track | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-12-31 | 2028-01-01 | +1 days | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
1%Awaiting acceptance
0%Not handed in
99%Deliverable flow
Display options
| Project plan & baseline023-D1 | 1% | CRT-023-01 | Approved | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | Iman Al-Jasem | 2026-11-11 | V1 | 3 of 3 |
| Monitoring & reporting023-D2 | 4% | — | Draft | Iman Al-JasemIman Al-JasemDirector General, Medium-Term PlanP-048iman.aljasem@psa.gov.sy | Iman Al-Jasem | 2026-12-23 | V0 | 0 of 3 |
| Business requirements023-D3 | 9% | — | Draft | Iman Al-JasemIman Al-JasemDirector General, Medium-Term PlanP-048iman.aljasem@psa.gov.sy | Iman Al-Jasem | 2027-02-02 | V0 | 0 of 3 |
| Solution design023-D4 | 9% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Iman Al-Jasem | 2027-03-16 | V0 | 0 of 3 |
| Release 1023-D5 | 14% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Iman Al-Jasem | 2027-04-26 | V0 | 0 of 3 |
| Release 2023-D6 | 14% | — | Draft | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | Iman Al-Jasem | 2027-06-07 | V0 | 0 of 3 |
| Integrations023-D7 | 14% | — | Draft | Iman Al-JasemIman Al-JasemDirector General, Medium-Term PlanP-048iman.aljasem@psa.gov.sy | Iman Al-Jasem | 2027-07-18 | V0 | 0 of 3 |
| System testing023-D8 | 10% | — | Draft | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | Iman Al-Jasem | 2027-08-29 | V0 | 0 of 3 |
| User acceptance testing023-D9 | 10% | — | Draft | Iman Al-JasemIman Al-JasemDirector General, Medium-Term PlanP-048iman.aljasem@psa.gov.sy | Iman Al-Jasem | 2027-10-09 | V0 | 0 of 3 |
| Training & change023-D10 | 8% | — | Draft | Iman Al-JasemIman Al-JasemDirector General, Medium-Term PlanP-048iman.aljasem@psa.gov.sy | Iman Al-Jasem | 2027-11-20 | V0 | 0 of 3 |
| Go-live & handover023-D11 | 7% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Iman Al-Jasem | 2027-12-31 | V0 | 0 of 3 |
| Total · 11 | 100% |