National Project Management Office (PMO)
- Code
- DOC-0205
- Version
- V2
- Date
- 2026-10-25
Updated corrective plan
Unified Government e-Services Platform
1. Where we stand
Earned progress is 58% against 67% planned; SPI 0.87, CPI 0.96. The forecast finish is 2027-05-12 instead of 2027-03-31 — a 42-day slip — with a 74% chance of further delay within 45 days if nothing is done.
2. Root causes
- Link-up records with the civil registry and the interoperability framework 11 weeks late
- Two vendor integration engineers left at the peak of the work
- The civil-registry test environment down nine days with no local fallback
3. Corrective actions
| Action | Owner | Due | Expected effect |
|---|---|---|---|
| A dedicated two-week integration sprint | Hamza Al-Hussein | 2026-11-20 | 14 days recovered |
| National-interface simulator | Eng. Saleh Al-Bakir | 2026-11-12 | Removes the stoppage risk |
| Two named engineers added to the vendor team | Eng. Tarek Al-Mardini | 2026-11-05 | 18 days recovered |
| A parallel UAT track | Joud Hammami | 2026-12-01 | 10 days recovered |
4. Financial effect
- Budget at completion
- SYP 2.16bn
- Estimate at completion
- SYP 2.25bn
- Cost of the corrective actions
- SYP 47.5M from contingency
- Target finish after correction
- 2027-04-10
Asked of the approver: approve the plan, release SYP 47.5M from the project contingency, and send a letter to the Ministry of Interior to extend the civil-registry test environment.
Project manager
Programme manager
President of the Authority