Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Updated corrective plan

InternalDraftV2

⁦The updated corrective plan to win back the 42⁩-day slip: an extra integration sprint, a simulator, a reinforced vendor team.

More
Showing version:

Internal

Syrian Arab Republic

Planning and Statistics Authority

National Project Management Office (PMO)

Code
DOC-0205
Version
V2
Date
2026-10-25

Updated corrective plan

Unified Government e-Services Platform

⁦1⁩. Where we stand

⁦Earned progress is 58% against 67% planned⁩; ⁦SPI 0⁩.⁦87⁩, ⁦CPI 0⁩.⁦96⁩. ⁦The forecast finish is 2027⁩⁦-05-12 instead of 2027⁩⁦-03-31⁩ — a ⁦42-day slip⁩ — ⁦with a 74% chance of further delay within 45 days if nothing is done⁩.

⁦2⁩. Root causes

  • ⁦Link-up records with the civil registry and the interoperability framework 11 weeks late⁩
  • Two vendor integration engineers left at the peak of the work
  • The civil-registry test environment down nine days with no local fallback

⁦3⁩. Corrective actions

ActionOwnerDueExpected effect
A dedicated two-week integration sprintHamza Al-Hussein⁦2026-11-20⁩⁦14 days recovered⁩
National-interface simulatorEng. Saleh Al-Bakir⁦2026-11-12⁩Removes the stoppage risk
Two named engineers added to the vendor teamEng. Tarek Al-Mardini⁦2026-11-05⁩⁦18 days recovered⁩
A parallel UAT trackJoud Hammami⁦2026-12-01⁩⁦10 days recovered⁩

⁦4⁩. Financial effect

Budget at completion
⁦SYP 2⁩.⁦16bn⁩
Estimate at completion
⁦SYP 2⁩.⁦25bn⁩
Cost of the corrective actions
⁦SYP 47⁩.⁦5M from contingency⁩
Target finish after correction
⁦2027-04-10⁩

Asked of the approver: approve the plan, ⁦release SYP 47⁩.⁦5M from the project contingency⁩, and send a letter to the Ministry of Interior to extend the civil-registry test environment.

Project manager

Eng. Tarek Al-Mardini

Programme manager

Eng. Lina Al-Attar

President of the Authority

Dr. Samer Al-Daqqar
Issued from Munjaz — valid only once approved electronically1 / 1

Internal

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close