Unified e-services platform — build & run contract
Unified Government e-Services Platform
The parties
This contract is made between the public body that owns the project (first party) and the contractor named in the data sheet (second party), under the public contracts law (Law 51 of 2004) and the general tender conditions.
- Project
- Unified Government e-Services Platform (PRJ-2026-014)
- Project manager
- Eng. Tarek Al-Mardini
- Budget
- SYP 2.16bn
- Progress
- 58% actual against 67% planned
- Forecast finish
- 2027-05-12
Key terms
- Delay penalty 0.5% a week, capped at 10% of the contract value
- A 10% performance bond valid until final acceptance
- 10% retention on every certificate
Addendum 1
This addendum amends the payment schedule and adds complementary works within 10% of the contract value.