PRJ-2026-014
Unified Government e-Services PlatformPlanned to date 67%
- SPI
- 0.87
- Forecast finish
- 2027-05-12
- Budget
- SYP 2.2B
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
Technical workshop with the vendor to close the civil-registry & interoperability integration.
Starts in
3 h 10 min2026-10-28 · 13:00
110 of 120 min
Civil-registry identity-check sequence
DiscussionEng. Rita Ghanem
40 min
Scenarios for pulling ministry data and collecting fees through the banks
DiscussionHamza Al-Hussein
40 min
Joint test plan
DecisionEng. Saleh Al-Bakir
30 min
What will be presented and what needs a decision — read before the meeting
Civil-registry identity-check sequence
DiscussionPresented by Eng. Rita Ghanem40 min
Scenarios for pulling ministry data and collecting fees through the banks
DiscussionPresented by Hamza Al-Hussein40 min
Joint test plan
DecisionPresented by Eng. Saleh Al-Bakir30 min
Needs a committee decision
From this committee’s earlier meetings and decisions — reviewed at the start
ACT-0301 · Eng. Tarek Al-Mardini
ACT-0306 · Eng. Tarek Al-Mardini
Project meeting — no quorum required
1 file
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
The summary is available once the meeting has been held and minuted.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-014
Unified Government e-Services PlatformPlanned to date 67%
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
Agenda item needing a decision
Joint test plan
From item 3
Change request awaiting decision · CR-2026-004
Add civil-record transfer & record merge to the first releaseUnified Government e-Services Platform
Corrective plan awaiting approval · CP-2026-01
Unified Government e-Services PlatformISS-0103 · Unified Government e-Services Platform
PeopleSYP 24.5M· Asked from: Change Committee
Three extra vendor integration engineers for four months through change request CR-2026-012
ISS-0101 · Unified Government e-Services Platform
Coordination· Asked from: Dr. Samer Al-Daqqar
A letter from the President of the Authority to the Ministry of Interior for a dedicated test environment for three months
CP-2026-01 · Unified Government e-Services Platform
PeopleSYP 24.5M· Asked from: Change Committee
Approve change request CR-2026-012 for three integration engineers
Nothing