CR-2026-004Unified Government e-Services Platform

Add civil-record transfer & record merge to the first release

ScopeIn reviewImpact level: ModerateDue tomorrow2026-10-29

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SYP 46.3M

Current budgetSYP 2.2B

After the changeSYP 2.2B

+2.1%

Schedule

+⁦21⁩ d
  • Baseline finish2027-03-31
  • New finish2027-04-21

Risk

+3
12Medium15High
Risk RSK-0003 · Late sign-off of service requirements by the owning ministries

Adds requirements the Ministry of Interior and the governorate offices must sign, and loads the integration team

Benefits

+7%

3,200 transfer and merge requests a month digitised six months early

⁦+7⁩% of expected benefits

Reason for change

The Ministry of Interior asked to bring civil-record transfer and record merge into the first release

Justification

About 3,200 transfer and merge requests come in a month; leaving the service for wave 2 keeps them on paper six more months and loads the civil-registry offices and service centres

PMO recommendation

Approve with conditions

The national PMO recommends conditional approval: add the service once the interoperability link is done, and win back part of the days through CR-2026-012

Conditions

  • The service does not start before the interoperability integration is complete
  • Approve CR-2026-012 to add integration capacity

Approval workflow

  1. Submitted

    Eng. Lina Al-Attar

    Done2026-10-15

  2. PM review

    Eng. Tarek Al-Mardini

    Done2026-10-16

  3. Impact analysis

    Kinan Azzam

    Done2026-10-20

  4. Finance & procurement

    Rasha Al-Mudarres

    Done2026-10-21

  5. Project owner’s acceptance

    Ibrahim Al-Saeed

    Done2026-10-21

  6. 6

    Change committee decision

    Dr. Ziad Al-Atassi

    Now2026-10-29

  7. 7

    Baseline updated

    Eng. Tarek Al-Mardini

    Later

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelModerateUp to SYP 125M and 90 days

  • Impact SYP 46.3M and 21 days — «moderate», so the Change Committee decides.
  • It has a financial link, so Finance & Procurement take part before the decision.
  • It changes scope or deliverables, so the project owner must accept it.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

Change Committee — meeting 4229 October 2026 13:00Meeting room 3 — fifth floor
  • Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairNot voted
  • Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouNot voted
  • Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syApprove
  • Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syApprove
  • Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syApprove with conditions
  • Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syAbstain
4/6Quorum met
  • Approve2
  • Approve with conditions1
  • Reject0
  • Abstain1

Quorum met · Awaiting the change committee’s decision in meeting ⁦42⁩