Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- PSA-PMO-F09
- Template edition
- 3.1
- Version
- V1
- Form date
- 2026-10-15
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-014
- Project
- Unified Government e-Services Platform
- Portfolio
- Digital Government Services & Data Portfolio
- Sector
- Digital Transformation Sector
- Sponsor
- Eng. Khaled Al-Kayyali
- Project manager
- Eng. Tarek Al-Mardini
1The change
- TitleAuto-filled
- Add civil-record transfer & record merge to the first release
- KindAuto-filled
- Scope
- Requested byAuto-filled
- Eng. Lina Al-Attar
- Raised onAuto-filled
- 2026-10-15
Reason
The Ministry of Interior asked to bring civil-record transfer and record merge into the first release
Justification
About 3,200 transfer and merge requests come in a month; leaving the service for wave 2 keeps them on paper six more months and loads the civil-registry offices and service centres
2Impact analysis
Cost
+SYP 46.3M
Schedule
+21 days
Risk
12 → 15
Benefits
+7%
Risk impact
Adds requirements the Ministry of Interior and the governorate offices must sign, and loads the integration team
Benefits impact
3,200 transfer and merge requests a month digitised six months early
3The approval decision
The PMO’s recommendation
The national PMO recommends conditional approval: add the service once the interoperability link is done, and win back part of the days through CR-2026-012
- Change Committee decision
- Not taken yet
- Decided on
- —
- Decision number
- —
Conditions
- The service does not start before the interoperability integration is complete
- Approve CR-2026-012 to add integration capacity
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Lina Al-AttarHead of the Unified Government e-Services Platform & Programme Manager, Government e-Services | Submitted | — | 2026-10-15 13:40 |
| 2 | Project manager | Technical acceptance | Eng. Tarek Al-MardiniProject manager | Approved | — | 2026-10-18 09:24 |
| 3 | PMO review & impact analysis | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | — | 2026-10-20 10:31 |
| 4 | Financial impact | Financial approval | Approval engineFinance | Pre-breach alert | — | 2026-10-22 08:00 |
Signatures
Project manager
Eng. Tarek Al-Mardini
Approved2026-10-18
PMO review & impact analysis
Mariam Al-Zoubi
Approved2026-10-20
Financial impact
Rasha Al-Mudarres
Awaiting decision
Contractual impact
Abdullah Al-Ujaili
Later
Change Committee
Dr. Ziad Al-Atassi
Later