Original
Original baseline
- Finish
- 2027-03-13
- −18 days
- Budget
- SYP 2.1B
- 53 activities
Approved at the planning gate with the original SYP 2.1bn budget and a March 2027 launch.
Approved 2025-02-16 · by Dr. Reem Al-Qabbani · via G3
One platform for 68 citizen e-services in a single journey — civil-status records, documents, building permits, local fees — checking identity against the civil registry and linking the ministries through the national interoperability framework.
Budget (BAC)
Actual cost
60% of budget
Progress
Estimate at completion
+SYP 90M
SPI · CPI
Forecast finish
42 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure31 March 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved at the planning gate with the original SYP 2.1bn budget and a March 2027 launch.
Approved 2025-02-16 · by Dr. Reem Al-Qabbani · via G3
Approved revised
CR-2026-001 added sign-in for legal agents and delegates: SYP 60M and 18 days on the critical path.
Approved 2026-02-24 · by Dr. Reem Al-Qabbani · via CR-2026-001
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Tarek Al-Mardini
What changed from version A to version B
Finish
2027-03-312027-05-12
+42 days
Budget
SYP 2.2BSYP 2.3B
+99.50 SYP M
Milestones moved
11 / 12
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference