CR-2026-001Unified Government e-Services Platform

Add an e-proxy service to act on someone else’s behalf

ScopeApprovedImpact level: Moderate

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SYP 60M

Current budgetSYP 2.1B

After the changeSYP 2.2B

+2.9%

Schedule

+⁦18⁩ d
  • Baseline finish2027-03-13
  • New finish2027-03-31

Risk

+4
12Medium16High
Risk RSK-0001 · Civil-registry identity and interoperability interfaces not ready on time

Adds more dependence on the civil-registry interfaces

Benefits

+18%

Lifts e-submitted transactions from 60% to 85%

⁦+18⁩% of expected benefits

Reason for change

The Ministries of Justice and Administrative Development asked for legal agents to complete transactions on an electronic power of attorney checked against the civil registry

Justification

40% of transactions are filed by agents for their owners; without an electronic power-of-attorney check they stay on paper

PMO recommendation

Approve

The national PMO recommends approval: the benefit clearly outweighs the cost

Approval workflow

  1. Submitted

    Eng. Tarek Al-Mardini

    Done2026-02-10

  2. PM review

    Eng. Tarek Al-Mardini

    Done2026-02-11

  3. Impact analysis

    Kinan Azzam

    Done2026-02-15

  4. Finance & procurement

    Rasha Al-Mudarres

    Done2026-02-16

  5. Project owner’s acceptance

    Ibrahim Al-Saeed

    Done2026-02-16

  6. Change committee decision

    Dr. Ziad Al-Atassi

    Done2026-02-23

  7. Baseline updated

    Eng. Tarek Al-Mardini

    Done2026-02-27

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelModerateUp to SYP 125M and 90 days

  • Impact SYP 60M and 18 days — «moderate», so the Change Committee decides.
  • It has a financial link, so Finance & Procurement take part before the decision.
  • It changes scope or deliverables, so the project owner must accept it.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

  • Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairApprove
  • Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouApprove
  • Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syApprove
  • Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syApprove
  • Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syApprove
  • Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syAbstain
6/6Quorum met
  • Approve5
  • Approve with conditions0
  • Reject0
  • Abstain1

Decided by the committee on 23 February 2026The decision in the log · DEC-2026-007

Baseline

Baseline updated on 27 February 2026