Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-014At risk4ExecutionHybridIn progressDelivered by:Ministry of Communications and Information Technology

Unified Government e-Services Platform

Remove from watchlist

One platform for 68 citizen e-services in a single journey — civil-status records, documents, building permits, local fees — checking identity against the civil registry and linking the ministries through the national interoperability framework.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 2.2B

Actual cost

SYP 1.3B

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SYP 2.3B

+SYP 90M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
PSA-PMO-F09
Template edition
3.1
Version
V2
Form date
⁦2026-02-10⁩
ApprovedCR-2026-001Add an e-proxy service to act on someone else’s behalf

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-014
Project
Unified Government e-Services Platform
Portfolio
Digital Government Services & Data Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Eng. Tarek Al-Mardini

1The change

TitleAuto-filled
Add an e-proxy service to act on someone else’s behalf
KindAuto-filled
Scope
Requested byAuto-filled
Eng. Tarek Al-Mardini
Raised onAuto-filled
⁦2026-02-10⁩

Reason

The Ministries of Justice and Administrative Development asked for legal agents to complete transactions on an electronic power of attorney checked against the civil registry

Justification

40% of transactions are filed by agents for their owners; without an electronic power-of-attorney check they stay on paper

2Impact analysis

Cost

+SYP 60M

Schedule

+18 days

Risk

12 → 16

Benefits

+18%

Risk impact

Adds more dependence on the civil-registry interfaces

Benefits impact

Lifts e-submitted transactions from 60% to 85%

3The approval decision

The PMO’s recommendation

The national PMO recommends approval: the benefit clearly outweighs the cost

Change Committee decision
Approve
Decided on
⁦2026-02-23⁩
Decision number
DEC-2026-007

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformSubmitted—⁦2026-02-10⁩ 10:19
2Project managerTechnical acceptanceEng. Tarek Al-MardiniProject managerApproved—⁦2026-02-11⁩ 12:33
3PMO review & impact analysisMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-02-12⁩ 13:40
4Financial impactFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-02-15⁩ 11:38
5Contractual impactFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2026-02-17⁩ 12:15
6Change CommitteeTechnical acceptanceDr. Ziad Al-AtassiChange CommitteeApproved—⁦2026-02-19⁩ 10:01

Signatures

Project manager

Eng. Tarek Al-Mardini

Approved⁦2026-02-11⁩

PMO review & impact analysis

Mariam Al-Zoubi

Approved⁦2026-02-12⁩

Financial impact

Rasha Al-Mudarres

Approved⁦2026-02-15⁩

Contractual impact

Abdullah Al-Ujaili

Approved⁦2026-02-17⁩

Change Committee

Dr. Ziad Al-Atassi

Approved⁦2026-02-19⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F09 · version V2

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Tarek Al-Mardini on ⁦2026-02-10⁩

  1. Technical acceptance

    Project manager

    Eng. Tarek Al-Mardini · Project manager

    Approved · ⁦2026-02-11⁩ at ⁦12:33⁩

  2. Methodology review

    PMO review & impact analysis

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-02-12⁩ at ⁦13:40⁩

  3. Financial approval

    Financial impact

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-02-15⁩ at ⁦11:38⁩

  4. Financial approval

    Contractual impact

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-02-17⁩ at ⁦12:15⁩

  5. Technical acceptance

    Change Committee

    Dr. Ziad Al-Atassi · Change Committee

    Approved · ⁦2026-02-19⁩ at ⁦10:01⁩

Steps that do not apply to this record

  • National Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Authority Executive Council — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-02-23⁩

    Approved by the committee

    Eng. Tarek Al-Mardini

  2. V1Returned for edit⁦2026-02-10⁩

    The request as raised

    Eng. Tarek Al-Mardini

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close