Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- PSA-PMO-F09
- Template edition
- 3.1
- Version
- V2
- Form date
- 2026-02-10
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-014
- Project
- Unified Government e-Services Platform
- Portfolio
- Digital Government Services & Data Portfolio
- Sector
- Digital Transformation Sector
- Sponsor
- Eng. Khaled Al-Kayyali
- Project manager
- Eng. Tarek Al-Mardini
1The change
- TitleAuto-filled
- Add an e-proxy service to act on someone else’s behalf
- KindAuto-filled
- Scope
- Requested byAuto-filled
- Eng. Tarek Al-Mardini
- Raised onAuto-filled
- 2026-02-10
Reason
The Ministries of Justice and Administrative Development asked for legal agents to complete transactions on an electronic power of attorney checked against the civil registry
Justification
40% of transactions are filed by agents for their owners; without an electronic power-of-attorney check they stay on paper
2Impact analysis
Cost
+SYP 60M
Schedule
+18 days
Risk
12 → 16
Benefits
+18%
Risk impact
Adds more dependence on the civil-registry interfaces
Benefits impact
Lifts e-submitted transactions from 60% to 85%
3The approval decision
The PMO’s recommendation
The national PMO recommends approval: the benefit clearly outweighs the cost
- Change Committee decision
- Approve
- Decided on
- 2026-02-23
- Decision number
- DEC-2026-007
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Tarek Al-MardiniProject Manager, Unified Government e-Services Platform | Submitted | — | 2026-02-10 10:19 |
| 2 | Project manager | Technical acceptance | Eng. Tarek Al-MardiniProject manager | Approved | — | 2026-02-11 12:33 |
| 3 | PMO review & impact analysis | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | — | 2026-02-12 13:40 |
| 4 | Financial impact | Financial approval | Rasha Al-MudarresFinance | Approved | — | 2026-02-15 11:38 |
| 5 | Contractual impact | Financial approval | Abdullah Al-UjailiProcurement & contracts | Approved | — | 2026-02-17 12:15 |
| 6 | Change Committee | Technical acceptance | Dr. Ziad Al-AtassiChange Committee | Approved | — | 2026-02-19 10:01 |
Signatures
Project manager
Eng. Tarek Al-Mardini
Approved2026-02-11
PMO review & impact analysis
Mariam Al-Zoubi
Approved2026-02-12
Financial impact
Rasha Al-Mudarres
Approved2026-02-15
Contractual impact
Abdullah Al-Ujaili
Approved2026-02-17
Change Committee
Dr. Ziad Al-Atassi
Approved2026-02-19