Solution & integration design

ConfidentialIn reviewV5Checked out to Eng. Rita Ghanem

The solution architecture and the integration map to the civil registry, the national interoperability framework, bank e-payment and the ministries’ systems, the request & service data model and the security and availability requirements.

More
Showing version:

Confidential

Syrian Arab Republic

Planning and Statistics Authority

National Project Management Office (PMO)

Code
DOC-0203
Version
V5
Date
2026-10-19

Solution & integration design

Unified Government e-Services Platform

⁦1⁩. Solution overview

The platform is the unified services portal, a request and forms engine, a central integration layer with the ministries’ systems and a request & service data store, ⁦hosted in the government data centre inside Syria with a 99⁩.⁦9% availability target⁩.

⁦2⁩. Integration map

PlatformPurposePatternStatus
Civil registryApplicant identity checkSynchronous — RESTIn testing
Ministry systemsRequest processing at the service-owning ministrySynchronous — RESTDone
National interoperability frameworkData exchange between public bodiesAsynchronous — messagingIn build
Bank e-paymentService-fee collection under the Central Bank of Syria frameworkNightly batchPlanned

Every interface goes through the central API gateway; the national interoperability framework uses asynchronous messaging so a slow reply from a ministry never blocks a citizen’s transaction, with automatic retries and an audit trail for every message.

⁦3⁩. Simulator & fallback

A local simulator of the civil-registry, interoperability and e-payment interfaces is built in the first integration sprint, so the team keeps working when the national test environments go down — as they did for nine days in September.

⁦4⁩. Data model

  • Beneficiary: national number, name, governorate, contacts, consents
  • Request: type (civil-registry extract, no-criminal-record, building permit, municipal fee), owning body, stage, attachments, time limit
  • Check: interoperability message number, issuing body, status, reply date
  • Log: every change with who, when and through which channel

⁦5⁩. Cybersecurity & data protection

  • Compliance with the national cybersecurity controls and the government cloud controls
  • Personal data encrypted at rest and in transit under the approved data-protection policy
  • An independent penetration test before launch with no critical or high findings
  • Round-the-clock monitoring from the security operations centre

Enterprise architect

Eng. Rita Ghanem

Architecture review

Eng. Nadine Ismail