PRJ-2026-014
Unified Government e-Services PlatformPlanned to date 67%
- SPI
- 0.87
- Forecast finish
- 2027-05-12
- Budget
- SYP 2.2B
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
Weekly project team meeting and corrective-plan follow-up.
Held on
26 October 202609:30 – 10:35
60 of 60 min
Wave 1 progress (24 government services)
For informationEng. Tarek Al-Mardini
20 min
Vendor integration engineer shortfall
DiscussionHamza Al-Hussein
25 min
Civil-registry test environment readiness
DiscussionHamza Al-Hussein
15 min
Saved as you type
No decisions recorded
Record the decision and put it to a vote if needed.
They show in the task register and on the owner’s calendar
ACT-0301Eng. Tarek Al-Mardini
Project meeting — no quorum required
1 file
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-014
Unified Government e-Services PlatformPlanned to date 67%
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
Change request awaiting decision · CR-2026-004
Add civil-record transfer & record merge to the first releaseUnified Government e-Services Platform
Corrective plan awaiting approval · CP-2026-01
Unified Government e-Services PlatformISS-0103 · Unified Government e-Services Platform
PeopleSYP 24.5M· Asked from: Change Committee
Three extra vendor integration engineers for four months through change request CR-2026-012
ISS-0101 · Unified Government e-Services Platform
Coordination· Asked from: Dr. Samer Al-Daqqar
A letter from the President of the Authority to the Ministry of Interior for a dedicated test environment for three months
CP-2026-01 · Unified Government e-Services Platform
PeopleSYP 24.5M· Asked from: Change Committee
Approve change request CR-2026-012 for three integration engineers
Nothing