Government data centre hosting capacity exceeded at launch

8MediumIn progress

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Load estimates assume 40% of expected users, while demand is expected to be higher at launch and in the local-fee payment seasons

Preventive controls

  • Load test at three times the expected use
  • Turn on auto-scaling in the government data centre hosting

2 / 2

Event

Government data centre hosting capacity exceeded at launch

8MediumTrigger

Response time above 3 seconds in the load test

Contingency

A staged launch by governorate, keeping the service at the citizen service centres as a fallback

Impact

Slow or unavailable document requests and fee payments in launch week, crowds back at the citizen service centres, and less trust in the platform

SYP 22.5M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
8Medium

Residual

5
4
3
2
1
1
2
3
4
5
3Low

Exposure

SYP 22.5M

Residual

⁦63⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 9 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Tarek Al-Mardini

    Currently followed up here
  2. 2

    Programme manager

    Eng. Lina Al-Attar

  3. 3

    PMO director

    Dr. Reem Al-Qabbani

  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Load test at three times the expected use

    Eng. Saleh Al-BakirEng. Saleh Al-BakirCloud & Integration EngineerP-034saleh.albakir@psa.gov.sy
    In progressIn 43 days2026-12-10
  • Turn on auto-scaling in the government data centre hosting

    Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy
    In progressIn 33 days2026-11-30

Trigger

Response time above 3 seconds in the load test

Contingency

A staged launch by governorate, keeping the service at the citizen service centres as a fallback