CR-2026-009Unified Government e-Services Platform
Extend the government data centre hosting contract by six months
Justification and the cost, schedule and risk impact, with a recommendation.
Impact analysis
Before and after — as it will show in the baseline if approved
Cost
+SYP 28.8MCurrent budgetSYP 2.2B
After the changeSYP 2.2B
+1.3%
Schedule
None- Baseline finish2027-03-31
- New finish2027-03-31
Risk
0No change in risk
Benefits
0%No effect on benefits
0% of expected benefits
Reason for change
The later launch extends hosting needs past the contract end
Justification
A hosting gap would stop development and test environments
PMO recommendation
ApproveImpact analysis in progress at the national PMO
Approval workflow
Submitted
Eng. Tarek Al-Mardini
Done2026-10-20
PM review
Eng. Tarek Al-Mardini
Done2026-10-21
- 3
Impact analysis
Kinan Azzam
Now2026-10-25
- 4
Finance & procurement
Rasha Al-Mudarres
Later
- 5
Change committee decision
Dr. Ziad Al-Atassi
Later2026-11-03
- 6
Baseline updated
Eng. Tarek Al-Mardini
Later
Why this route
The route is built from the request’s kind and impact level under the approved authority matrix.
Impact levelModerateUp to SYP 125M and 90 days
- Impact SYP 28.8M and 0 days — «moderate», so the Change Committee decides.
- It touches a signed contract, so Finance & Procurement review it contractually.
Change committee vote
Members vote before or during the meeting; the decision is taken once quorum is met
- Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairNot voted
- Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouNot voted
- Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syNot voted
- Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syNot voted
- Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syNot voted
- Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syNot voted
- Approve0
- Approve with conditions0
- Reject0
- Abstain0
Awaiting the impact analysis