PRJ-2026-014At risk4ExecutionHybridIn progressDelivered by:Ministry of Communications and Information Technology

Unified Government e-Services Platform

Remove from watchlist

One platform for 68 citizen e-services in a single journey — civil-status records, documents, building permits, local fees — checking identity against the civil registry and linking the ministries through the national interoperability framework.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 2.2B

Actual cost

SYP 1.3B

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SYP 2.3B

+SYP 90M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

6Achieved
0On track
5At risk
1Late
Average delay28 days
Jan 25Apr 25Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27
Contractual
Build & run contract signedPlanned: ⁦2025-04-30⁩Forecast / actual: ⁦2025-05-04⁩Delay: 4 days02 +4
Wave 1 development complete (24 services)Planned: ⁦2026-09-30⁩Forecast / actual: ⁦2026-11-12⁩Delay: 43 days07 +43
Executive
Charter approvedPlanned: ⁦2025-01-05⁩Forecast / actual: ⁦2025-01-05⁩01
Official launch of the unified government e-services platformPlanned: ⁦2027-03-01⁩Forecast / actual: ⁦2027-04-15⁩Delay: 45 days11 +45
Payment
Advance payment (10%) releasedPlanned: ⁦2025-05-25⁩Forecast / actual: ⁦2025-06-01⁩Delay: 7 days03 +7
Final acceptance & final paymentPlanned: ⁦2027-03-31⁩Forecast / actual: ⁦2027-05-12⁩Delay: 42 days12 +42
Regulatory
Data classification approved under the data-protection policyPlanned: ⁦2026-06-30⁩Forecast / actual: ⁦2026-07-14⁩Delay: 14 days06 +14
Penetration test passed, security sign-offPlanned: ⁦2026-12-15⁩Forecast / actual: ⁦2027-01-28⁩Delay: 44 days09 +44
Project
Requirements & design signed offPlanned: ⁦2025-09-30⁩Forecast / actual: ⁦2025-10-21⁩Delay: 21 days04 +21
Internal pilot (MVP) livePlanned: ⁦2026-03-31⁩Forecast / actual: ⁦2026-04-28⁩Delay: 28 days05 +28
Civil registry & national interoperability integration completePlanned: ⁦2026-10-31⁩Forecast / actual: ⁦2026-12-10⁩Delay: 40 days08 +40
User acceptance testing completePlanned: ⁦2027-01-31⁩Forecast / actual: ⁦2027-03-14⁩Delay: 42 days10 +42

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦12⁩ results
Export CSV
Charter approvedMS-01Executive⁦2025-01-05⁩⁦2025-01-05⁩On timeEng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.syAchieved1Approved
Build & run contract signedMS-02Contractual⁦2025-04-30⁩⁦2025-05-04⁩⁦+4⁩ daysOmar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syAchieved2Approved
Advance payment (10%) releasedMS-03Payment⁦2025-05-25⁩⁦2025-06-01⁩⁦+7⁩ daysOmar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syAchieved2Approved
Requirements & design signed offMS-04Project⁦2025-09-30⁩⁦2025-10-21⁩⁦+21⁩ daysHiba Al-ShamiHiba Al-ShamiSenior Business Analyst — Government ServicesP-006hiba.alshami@psa.gov.syAchieved2Approved
Internal pilot (MVP) liveMS-05Project⁦2026-03-31⁩⁦2026-04-28⁩⁦+28⁩ daysEng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.syAchieved2Approved
Data classification approved under the data-protection policyMS-06Regulatory⁦2026-06-30⁩⁦2026-07-14⁩⁦+14⁩ daysRazan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.syAchieved1Approved
Wave 1 development complete (24 services)MS-07Contractual⁦2026-09-30⁩⁦2026-11-12⁩⁦+43⁩ daysEng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.syLate1Not requested
Civil registry & national interoperability integration completeMS-08Project⁦2026-10-31⁩⁦2026-12-10⁩⁦+40⁩ daysHamza Al-HusseinHamza Al-HusseinSenior Software Engineer – IntegrationP-030hamza.alhussein@psa.gov.syAt risk0Not requested
Penetration test passed, security sign-offMS-09Regulatory⁦2026-12-15⁩⁦2027-01-28⁩⁦+44⁩ daysEng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.syAt risk0Not requested
User acceptance testing completeMS-10Project⁦2027-01-31⁩⁦2027-03-14⁩⁦+42⁩ daysJoud HammamiJoud HammamiQA & Testing SpecialistP-033joud.hammami@psa.gov.syAt risk0Not requested
Official launch of the unified government e-services platformMS-11Executive⁦2027-03-01⁩⁦2027-04-15⁩⁦+45⁩ daysEng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.syAt risk0Not requested
Final acceptance & final paymentMS-12Payment⁦2027-03-31⁩⁦2027-05-12⁩⁦+42⁩ daysOmar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syAt risk0Not requested
⁦1⁩–⁦12⁩ of ⁦12⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦58%⁩

Awaiting acceptance

⁦23%⁩

Not handed in

⁦19%⁩

Deliverable flow

Pick a stage to filter the register
⁦13⁩ results
Export CSV
Business requirements documentDLV-01⁦10%⁩CRT-014-01ApprovedHiba Al-ShamiHiba Al-ShamiSenior Business Analyst — Government ServicesP-006hiba.alshami@psa.gov.syEng. Lina Al-Attar⁦2025-08-31⁩V4⁦3⁩ of ⁦3⁩
UX prototypeDLV-02⁦6%⁩CRT-014-02ApprovedYasmine BitarYasmine BitarFront-end Developer (Contractor)P-044yasmine.bitar@psa.gov.syHiba Al-Shami⁦2025-09-15⁩V3⁦3⁩ of ⁦3⁩
Solution & integration designDLV-03⁦6%⁩—Under reviewEng. Rita GhanemEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syEng. Nadine Ismail⁦2026-10-15⁩V5⁦2⁩ of ⁦4⁩
Wave 1 service package (24 services)DLV-04⁦14%⁩—SubmittedEng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.syJoud Hammami⁦2026-09-30⁩V1⁦1⁩ of ⁦3⁩
Civil-registry identity-check interfacesDLV-05⁦5%⁩—DraftHamza Al-HusseinHamza Al-HusseinSenior Software Engineer – IntegrationP-030hamza.alhussein@psa.gov.syEng. Hussam Zeidan⁦2026-10-31⁩V2⁦1⁩ of ⁦3⁩
National interoperability framework interfacesDLV-06⁦5%⁩—DraftHamza Al-HusseinHamza Al-HusseinSenior Software Engineer – IntegrationP-030hamza.alhussein@psa.gov.syDr. Firas Al-Obaid⁦2026-11-15⁩V1⁦0⁩ of ⁦3⁩
Data migration planDLV-07⁦3%⁩—ReturnedMoaz KaddourMoaz KaddourData EngineerP-032moaz.kaddour@psa.gov.syEng. Rita Ghanem⁦2026-10-10⁩V2⁦1⁩ of ⁦3⁩
Master test planDLV-08⁦4%⁩CRT-014-08ApprovedJoud HammamiJoud HammamiQA & Testing SpecialistP-033joud.hammami@psa.gov.syEng. Tarek Al-Mardini⁦2026-06-30⁩V3⁦3⁩ of ⁦3⁩
Performance & load test reportDLV-09⁦3%⁩—DraftEng. Saleh Al-BakirEng. Saleh Al-BakirCloud & Integration EngineerP-034saleh.albakir@psa.gov.syEng. Rita Ghanem⁦2026-12-20⁩V0⁦0⁩ of ⁦2⁩
Change management & training planDLV-10⁦3%⁩—SubmittedOla Al-JandaliOla Al-JandaliChange Management SpecialistP-035ola.aljandali@psa.gov.syEng. Lina Al-Attar⁦2026-10-31⁩V2⁦3⁩ of ⁦3⁩
User & operator guideDLV-11⁦3%⁩—DraftHiba Al-ShamiHiba Al-ShamiSenior Business Analyst — Government ServicesP-006hiba.alshami@psa.gov.syOla Al-Jandali⁦2027-02-15⁩V0⁦0⁩ of ⁦2⁩
Internal pilot: the core platform and three servicesDLV-12⁦30%⁩CRT-014-12ApprovedEng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.syEng. Lina Al-Attar⁦2026-03-31⁩V2⁦3⁩ of ⁦3⁩
Approved service-data classification registerDLV-13⁦8%⁩CRT-014-13ApprovedMoaz KaddourMoaz KaddourData EngineerP-032moaz.kaddour@psa.gov.syRazan Al-Rifai⁦2026-06-30⁩V2⁦3⁩ of ⁦3⁩
Total · 13⁦100%⁩
⁦1⁩–⁦13⁩ of ⁦13⁩