PRJ-2026-014At risk4ExecutionHybridIn progressDelivered by:Ministry of Communications and Information Technology

Unified Government e-Services Platform

Remove from watchlist

One platform for 68 citizen e-services in a single journey — civil-status records, documents, building permits, local fees — checking identity against the civil registry and linking the ministries through the national interoperability framework.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 2.2B

Actual cost

SYP 1.3B

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SYP 2.3B

+SYP 90M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
PSA-PMO-F08
Template edition
1.1
Version
V2
Form date
⁦2026-07-14⁩
ApprovedCRT-014-13Approved service-data classification register

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-014
Project
Unified Government e-Services Platform
Portfolio
Digital Government Services & Data Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Eng. Tarek Al-Mardini

1The deliverableAuto-filled

DeliverableAuto-filled
Approved service-data classification register
DescriptionAuto-filled
The classification register of citizen, agent and transaction data under the approved data-protection policy, with each data entity’s owner and sharing rules.
OwnerAuto-filled
Moaz Kaddour
VersionAuto-filled
V2
Weight in the projectAuto-filled
⁦8%⁩
DueAuto-filled
⁦2026-06-30⁩

2Evidence of completionAuto-filled

FileVersionByDate
data-classification_register_v2.xlsxV2Moaz Kaddour⁦2026-07-12⁩

3Inspection and acceptance criteria

CriterionResult
Every data entity classifiedMet
An owner named for every data entityMet
Approved by the Data & AI DirectorateMet
Met3 of 3
InspectorAuto-filled
Razan Al-Rifai
Accepted byAuto-filled
Eng. Lina Al-Attar
Acceptance note
The register is complete and approved, and was included in the July payment certificate.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Data classification approved under the data-protection policy
ContractAuto-filled
CTR-2025-007
Payment certificateAuto-filled
PAY-2026-004
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Moaz KaddourData EngineerSubmitted—⁦2026-07-02⁩ 12:09
2Evidence against the acceptance criteriaMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-07-06⁩ 12:51
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Lina Al-AttarProject ownerOn behalf of Ibrahim Al-SaeedApprovedThe register is complete and approved, and was included in the July payment certificate.⁦2026-07-08⁩ 13:58
4Deliverable matched to the contract lineFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2026-07-09⁩ 11:32
5Certificate linked to the payment certificateFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-07-13⁩ 12:09

Signatures

Evidence against the acceptance criteria

Mariam Al-Zoubi

Approved⁦2026-07-06⁩

Inspection & technical acceptance — owner

Eng. Lina Al-Attar

Approved⁦2026-07-08⁩

Deliverable matched to the contract line

Abdullah Al-Ujaili

Approved⁦2026-07-09⁩

Certificate linked to the payment certificate

Rasha Al-Mudarres

Approved⁦2026-07-13⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F08 · version V2

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Moaz Kaddour on ⁦2026-07-02⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-07-06⁩ at ⁦12:51⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Ibrahim Al-Saeed · Project owner

    Approved · ⁦2026-07-08⁩ at ⁦13:58⁩ · On behalf of Ibrahim Al-Saeed (Eng. Lina Al-Attar)

    The register is complete and approved, and was included in the July payment certificate.

  3. Financial approval

    Deliverable matched to the contract line

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-07-09⁩ at ⁦11:32⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-07-13⁩ at ⁦12:09⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-07-12⁩

    data-classification_register_v2.xlsx

    Moaz Kaddour

Only one version so far.