PRJ-2026-014At risk4ExecutionHybridIn progressDelivered by:Ministry of Communications and Information Technology

Unified Government e-Services Platform

Remove from watchlist

One platform for 68 citizen e-services in a single journey — civil-status records, documents, building permits, local fees — checking identity against the civil registry and linking the ministries through the national interoperability framework.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 2.2B

Actual cost

SYP 1.3B

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SYP 2.3B

+SYP 90M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
PSA-PMO-F08
Template edition
1.1
Version
V4
Form date
⁦2025-09-14⁩
ApprovedCRT-014-01Business requirements document

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-014
Project
Unified Government e-Services Platform
Portfolio
Digital Government Services & Data Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Eng. Tarek Al-Mardini

1The deliverableAuto-filled

DeliverableAuto-filled
Business requirements document
DescriptionAuto-filled
Functional and non-functional requirements for 68 government e-services with to-be procedure maps.
OwnerAuto-filled
Hiba Al-Shami
VersionAuto-filled
V4
Weight in the projectAuto-filled
⁦10%⁩
DueAuto-filled
⁦2025-08-31⁩

2Evidence of completionAuto-filled

FileVersionByDate
BRD_unified-services_v4.docxV4Hiba Al-Shami⁦2025-09-10⁩
process-maps_68-services.zipV4Hiba Al-Shami⁦2025-09-10⁩

3Inspection and acceptance criteria

CriterionResult
All 68 services mapped and signedMet
Requirements traceability matrix completeMet
Signed by the service-owning ministriesMet
Met3 of 3
InspectorAuto-filled
Eng. Lina Al-Attar
Accepted byAuto-filled
Basel Al-Mahayni
Acceptance note
The document matches the scope and is signed by all four service-owning ministries.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Requirements & design signed off
ContractAuto-filled
CTR-2025-007
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Hiba Al-ShamiSenior Business Analyst — Government ServicesSubmitted—⁦2025-08-24⁩ 09:18
2Evidence against the acceptance criteriaMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-08-25⁩ 09:30
3Inspection & technical acceptance — ownerTechnical acceptanceBasel Al-MahayniProject ownerOn behalf of Ibrahim Al-SaeedApprovedThe document matches the scope and is signed by all four service-owning ministries.⁦2025-08-27⁩ 10:37
4Deliverable matched to the contract lineFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2025-08-31⁩ 14:41
5Certificate linked to the payment certificateFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-09-01⁩ 09:18

Signatures

Evidence against the acceptance criteria

Mariam Al-Zoubi

Approved⁦2025-08-25⁩

Inspection & technical acceptance — owner

Basel Al-Mahayni

Approved⁦2025-08-27⁩

Deliverable matched to the contract line

Abdullah Al-Ujaili

Approved⁦2025-08-31⁩

Certificate linked to the payment certificate

Rasha Al-Mudarres

Approved⁦2025-09-01⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F08 · version V4

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Hiba Al-Shami on ⁦2025-08-24⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-08-25⁩ at ⁦09:30⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Ibrahim Al-Saeed · Project owner

    Approved · ⁦2025-08-27⁩ at ⁦10:37⁩ · On behalf of Ibrahim Al-Saeed (Basel Al-Mahayni)

    The document matches the scope and is signed by all four service-owning ministries.

  3. Financial approval

    Deliverable matched to the contract line

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-08-31⁩ at ⁦14:41⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-09-01⁩ at ⁦09:18⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V4ApprovedCurrent⁦2025-09-10⁩

    BRD_unified-services_v4.docx

    Hiba Al-Shami

Only one version so far.