Change requests, their impact analysis and the CCB approval path.
of 16 this year
meeting 42 — tomorrow
all open requests
extra days on projects
worth SYP 1.9B
29 October 2026 · 13:00Meeting room 3 — fifth floor
Agenda
From submission to the approval decision — click a stage to filter the list
Cost impact by kind of change
All requests this year
SYP 3.4B
Total
Every request is routed by its kind and impact level; this is the rule the route reads.
| Kind of request | MinorUp to SYP 25M and no extra days | ModerateUp to SYP 125M and 90 days | MajorAbove SYP 125M or 90 days |
|---|---|---|---|
| Scope |
|
|
|
| Budget |
|
|
|
| Schedule |
|
|
|
| Deliverables |
|
|
|
| Contract |
|
|
|
| Resources |
|
|
|
Any change to scope, budget, schedule, deliverables, contract or resources comes through here.
Display options
| Unified Government e-Services Platform | Resources | +SYP 24.5M | −12 d | Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.sy | 2026-10-26 | In 12 days2026-11-09 | 0/6 | Submitted | |
| Unified Government e-Services Platform | Contract | +SYP 28.8M | None | Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.sy | 2026-10-20 | In 6 days2026-11-03 | — | Submitted | |
| Government Fibre Backbone — Damascus–Homs Segment | Scope | +SYP 30M | +20 d | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | 2026-10-19 | In 5 days2026-11-02 | — | Submitted | |
| Unified Government e-Services Platform | Scope | +SYP 46.3M | +21 d | Eng. Lina Al-AttarEng. Lina Al-AttarHead of the Unified Government e-Services Platform & Programme Manager, Government e-ServicesP-004lina.alattar@psa.gov.sy | 2026-10-15 | Due tomorrow2026-10-29 | 4/6 | In review | |
| Integrated Public Financial Management System — Phase 1 | Budget | +SYP 170M | +45 d | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | 2026-10-09 | In 2 days2026-10-30 | 2/6 | In review | |
| Sheikh Najjar Industrial City Rehabilitation | Scope | +SYP 562.5M | +75 d | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | 2026-10-06 | 1 day overdue2026-10-27 | 0/6 | Submitted | |
CR-2026-006 Extend the contract by 150 days | Hama National Hospital Upgrade & Extension | Schedule | — | +150 d | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | 2026-10-01 | 6 days overdue2026-10-22 | 0/6 | In review |
| Douma Wastewater Treatment Plant | Scope | +SYP 210M | +55 d | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | 2026-09-28 | 9 days overdue2026-10-19 | 4/6 | In review | |
| Government Services Mobile App — New Release | Deliverables | +SYP 8M | +10 d | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | 2026-09-14 | 2026-09-282026-09-28 | 6/6 | Deferred | |
| Hama National Hospital Upgrade & Extension | Contract | +SYP 465M | +40 d | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | 2026-08-20 | 55 days overdue2026-09-03 | 6/6 | Escalated | |
| Ministry of Finance e-Archiving | Deliverables | +SYP 16.3M | +30 d | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | 2026-08-11 | 2026-08-252026-08-25 | 6/6 | Rejected | |
CR-2026-013 Replace the cooling-unit supplier | Government Backup Data Centre, Homs — Phase 2 | Contract | +SYP 77.5M | +14 d | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | 2026-05-17 | 2026-05-312026-05-31 | 6/6 | Approved |
CR-2026-011 Redesign internal roads for heavy trucks | Sheikh Najjar Industrial City Rehabilitation | Scope | +SYP 240M | +20 d | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | 2026-04-12 | 2026-04-262026-04-26 | 6/6 | Approved |
CR-2026-002 Add a basement parking level to block 3 | Darayya Replacement Housing | Scope | +SYP 962.5M | +60 d | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | 2026-03-02 | 2026-03-232026-03-23 | 6/6 | Approved |
| Unified Government e-Services Platform | Scope | +SYP 60M | +18 d | Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.sy | 2026-02-10 | 2026-02-242026-02-24 | 6/6 | Approved | |
CR-2026-003 Add two spare bays at substation 4 | Aleppo 230 kV Substations Rehabilitation | Scope | +SYP 535M | +45 d | Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy | 2026-01-18 | 2026-02-082026-02-08 | 6/6 | Approved |