CR-2026-011Sheikh Najjar Industrial City Rehabilitation

Redesign internal roads for heavy trucks

ScopeApprovedImpact level: Major

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SYP 240M

Current budgetSYP 6.9B

After the changeSYP 7.2B

+3.5%

Schedule

+⁦20⁩ d
  • Baseline finish2027-03-11
  • New finish2027-03-31

Risk

−3
9Medium6Low

Removes the risk of resurfacing after opening

Benefits

+6%

40 km of roads ready for heavy trucks from day one

⁦+6⁩% of expected benefits

Reason for change

Returning heavy factories need internal roads with higher axle loads and wider roundabouts the design left out

Justification

Changing it now is cheaper than resurfacing 40 kilometres after opening

PMO recommendation

Approve

The national PMO recommends approval

Approval workflow

  1. Submitted

    Eng. Youssef Shehabi

    Done2026-04-12

  2. PM review

    Eng. Youssef Shehabi

    Done2026-04-13

  3. Impact analysis

    Kinan Azzam

    Done2026-04-17

  4. Finance & procurement

    Rasha Al-Mudarres

    Done2026-04-18

  5. Project owner’s acceptance

    Eng. Wassim Al-Azm

    Done2026-04-18

  6. Change committee recommendation

    Dr. Ziad Al-Atassi

    Done2026-04-18

  7. Executive Council decision

    Dr. Samer Al-Daqqar

    Done2026-04-21

  8. Baseline updated

    Eng. Youssef Shehabi

    Done2026-04-25

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelMajorAbove SYP 125M or 90 days

  • A cost impact of SYP 240M is above SYP 125M — «major»: the Change Committee recommends and the Executive Council decides.
  • It has a financial link, so Finance & Procurement take part before the decision.
  • It changes scope or deliverables, so the project owner must accept it.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

  • Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairApprove
  • Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouApprove
  • Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syApprove
  • Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syApprove
  • Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syApprove
  • Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syApprove
6/6Quorum met
  • Approve6
  • Approve with conditions0
  • Reject0
  • Abstain0

Decided by the committee on 21 April 2026The decision in the log · DEC-2026-033

Baseline

Baseline updated on 25 April 2026