PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection

Sheikh Najjar Industrial City Rehabilitation

Remove from watchlist

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 7.2B

Actual cost

SYP 3.1B

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 8B

+SYP 883.7M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2027-03-31⁩
    Budget
    SYP 6.9B
    ⁦17⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2024-09-01⁩ · by Eng. Bashir Al-Tai

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-06-30⁩
    ⁦+91⁩ days
    Budget
    SYP 7.7B
    ⁦17⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Youssef Shehabi

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2027-03-31⁩⁦2027-06-30⁩

⁦+91⁩ days

Budget

SYP 6.9BSYP 7.7B

⁦+802.50⁩ SYP M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2025-072026-012026-072027-012027-07
  • Project plan approved⁦+172⁩
  • Designs approved⁦+303⁩
  • Build complete⁦+294⁩
  • Testing & acceptance complete⁦+172⁩
  • Final handover⁦+91⁩

Version AVersion B

Cost by WBS element

Difference in SYP millions from A to B

  • 1Management & governance⁦+65.56⁩
  • 2Design & permits⁦+131.13⁩
  • 3Civil works⁦+331.17⁩
  • 4MEP works⁦+413.25⁩
  • 5Handover⁦+192.85⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Youssef Shehabi
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2024-09-01⁩by Eng. Bashir Al-Tai