PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection

Sheikh Najjar Industrial City Rehabilitation

Remove from watchlist

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 7.2B

Actual cost

SYP 3.1B

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 8B

+SYP 883.7M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
0On track
2At risk
1Late
Average delay206 days
Apr 25Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27Jul 27
Contractual
Build completePlanned: ⁦2026-03-23⁩Forecast / actual: ⁦2027-01-11⁩Delay: 294 daysG3 +294
Executive
Project plan approvedPlanned: ⁦2025-03-14⁩Forecast / actual: ⁦2025-09-02⁩Delay: 172 daysG1 +172
Payment
Final handoverPlanned: ⁦2027-03-31⁩Forecast / actual: ⁦2027-06-30⁩Delay: 91 daysG5 +91
Regulatory
Testing & acceptance completePlanned: ⁦2026-11-02⁩Forecast / actual: ⁦2027-04-23⁩Delay: 172 daysG4 +172
Project
Designs approvedPlanned: ⁦2025-08-11⁩Forecast / actual: ⁦2026-06-10⁩Delay: 303 daysG2 +303

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-03-14⁩⁦2025-09-02⁩⁦+172⁩ daysEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syAchieved1Approved
Designs approvedMS-G2Project⁦2025-08-11⁩⁦2026-06-10⁩⁦+303⁩ daysEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syAchieved1Approved
Build completeMS-G3Contractual⁦2026-03-23⁩⁦2027-01-11⁩⁦+294⁩ daysEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syLate0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2026-11-02⁩⁦2027-04-23⁩⁦+172⁩ daysEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syAt risk0Not requested
Final handoverMS-G5Payment⁦2027-03-31⁩⁦2027-06-30⁩⁦+91⁩ daysEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦39%⁩

Awaiting acceptance

⁦11%⁩

Not handed in

⁦50%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline006-D1⁦4%⁩CRT-006-01ApprovedEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syEng. Wassim Al-Azm⁦2024-12-29⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting006-D2⁦4%⁩CRT-006-02ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2025-03-14⁩V1⁦3⁩ of ⁦3⁩
Detailed design006-D3⁦8%⁩CRT-006-03ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2025-05-28⁩V1⁦3⁩ of ⁦3⁩
Permits & approvals006-D4⁦7%⁩CRT-006-04ApprovedEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syEng. Wassim Al-Azm⁦2025-08-11⁩V1⁦3⁩ of ⁦3⁩
Site works & excavation006-D5⁦16%⁩CRT-006-05ApprovedEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syEng. Wassim Al-Azm⁦2025-10-24⁩V1⁦3⁩ of ⁦3⁩
Structure006-D6⁦11%⁩—Under reviewEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syEng. Wassim Al-Azm⁦2026-01-07⁩V1⁦1⁩ of ⁦3⁩
Finishes006-D7⁦11%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-03-23⁩V0⁦0⁩ of ⁦3⁩
Supply006-D8⁦9%⁩—DraftEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syEng. Wassim Al-Azm⁦2026-06-05⁩V0⁦0⁩ of ⁦3⁩
Installation006-D9⁦9%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-08-19⁩V0⁦0⁩ of ⁦3⁩
Testing & commissioning006-D10⁦9%⁩—DraftEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syEng. Wassim Al-Azm⁦2026-11-02⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance006-D11⁦6%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2027-01-15⁩V0⁦0⁩ of ⁦3⁩
Final acceptance006-D12⁦6%⁩—DraftEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syEng. Wassim Al-Azm⁦2027-03-31⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩
⁦1⁩–⁦12⁩ of ⁦12⁩