Sheikh Najjar Industrial City Rehabilitation
Remove from watchlistRehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.
Budget (BAC)
Actual cost
44% of budget
Progress
Estimate at completion
+SYP 883.7M
SPI · CPI
Forecast finish
95 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure15 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-03-14 | 2025-09-02 | +172 days | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-08-11 | 2026-06-10 | +303 days | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-03-23 | 2027-01-11 | +294 days | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-02 | 2027-04-23 | +172 days | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-03-31 | 2027-06-30 | +91 days | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
39%Awaiting acceptance
11%Not handed in
50%Deliverable flow
Display options
| Project plan & baseline006-D1 | 4% | CRT-006-01 | Approved | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | Eng. Wassim Al-Azm | 2024-12-29 | V1 | 3 of 3 |
| Monitoring & reporting006-D2 | 4% | CRT-006-02 | Approved | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2025-03-14 | V1 | 3 of 3 |
| Detailed design006-D3 | 8% | CRT-006-03 | Approved | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2025-05-28 | V1 | 3 of 3 |
| Permits & approvals006-D4 | 7% | CRT-006-04 | Approved | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Eng. Wassim Al-Azm | 2025-08-11 | V1 | 3 of 3 |
| Site works & excavation006-D5 | 16% | CRT-006-05 | Approved | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Eng. Wassim Al-Azm | 2025-10-24 | V1 | 3 of 3 |
| Structure006-D6 | 11% | — | Under review | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | Eng. Wassim Al-Azm | 2026-01-07 | V1 | 1 of 3 |
| Finishes006-D7 | 11% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-03-23 | V0 | 0 of 3 |
| Supply006-D8 | 9% | — | Draft | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | Eng. Wassim Al-Azm | 2026-06-05 | V0 | 0 of 3 |
| Installation006-D9 | 9% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-08-19 | V0 | 0 of 3 |
| Testing & commissioning006-D10 | 9% | — | Draft | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Eng. Wassim Al-Azm | 2026-11-02 | V0 | 0 of 3 |
| Provisional acceptance006-D11 | 6% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2027-01-15 | V0 | 0 of 3 |
| Final acceptance006-D12 | 6% | — | Draft | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Eng. Wassim Al-Azm | 2027-03-31 | V0 | 0 of 3 |
| Total · 12 | 100% |