Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection

Sheikh Najjar Industrial City Rehabilitation

Remove from watchlist

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 7.2B

Actual cost

SYP 3.1B

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 8B

+SYP 883.7M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Scope statementRequired at this stage

What the project delivers, what it does not, and when a deliverable counts as accepted.

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

In scope

  • Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.
  • Syrian Arab Building Code compliance
  • Consultant-approved drawings

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the project owner
  • Main deliverable — final stageMeets the approved specification, signed off by the project owner

Scope baselineRequired at this stage

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2024-10-16⁩

    Baseline approved at the planning gate

    BudgetSYP7.2BFinish⁦2027-03-31⁩

Requirements registerRequired at this stage

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional1
  • Technical1
  • Regulatory2
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦33%⁩

2/6 · test result is a pass

Accepted

⁦33%⁩

2/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-006-01A building ready to receive its usersBusinessMustIn progressEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sySB-1
REQ-006-02Match the approved drawingsTechnicalMustIn progressEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sySB-1
REQ-006-03Smart building systemsFunctionalMustApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sySB-1
REQ-006-04Syrian Arab Building CodeRegulatoryCouldApprovedEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sySB-1
REQ-006-05Health & safetyRegulatoryShouldIn progressEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sySB-1
REQ-006-06CCTV and access controlSecurityShouldIn progressEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sySB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrixRequired at this stage

Requirement → deliverable → task → test → acceptance. No requirement has a gap.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close