PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection
Sheikh Najjar Industrial City Rehabilitation
Remove from watchlist
Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.
Early warning: 84% chance of slipping within 45 days
Budget (BAC)
SYP 7.2B
Actual cost
SYP 3.1B
44% of budget
Progress
39%Awaiting acceptance 11%
Estimate at completion
SYP 8B
+SYP 883.7M
SPI · CPI
0.78Schedule performance index · 0.780.89Cost performance index · 0.89
Forecast finish
2027-07-04
95 days behind baseline
Execution·Stage 4 of 5
Next gate:Closure15 January 2027
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.