PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection

Sheikh Najjar Industrial City Rehabilitation

Remove from watchlist

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 7.2B

Actual cost

SYP 3.1B

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 8B

+SYP 883.7M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Closure readiness

Closure planned after the forecast finish on ⁦2027-07-04⁩

A preview of what closure will need, with the planned dates, and the lessons captured so far.

0/7

Closure checklist

Seven mandatory items before any project closes.

  1. 1

    Deliverables acceptedNot started

    Final acceptance of every deliverable

    Eng. Wassim Al-AzmPlanned ⁦2027-06-24⁩

  2. 2

    Financial closureNot started

    Spend reconciled, commitments closed

    Omar Al-NahhasPlanned ⁦2027-07-24⁩

  3. 3

    Contract closureNot started

    Contracts closed, bonds released

    Omar Al-NahhasPlanned ⁦2027-08-03⁩

  4. 4

    Documents archivedNot started

    Documents archived with classification

    Eng. Youssef ShehabiPlanned ⁦2027-07-29⁩

  5. 5

    Lessons learnedNot started

    Lessons-learned session

    Eng. Youssef ShehabiPlanned ⁦2027-07-19⁩

  6. 6

    Benefits owner assignedNot started

    Benefits handed to their owner with a measurement plan

    Eng. Wassim Al-AzmPlanned ⁦2027-07-14⁩

  7. 7

    Final report approvedNot started

    Final report and its approval

    Eng. Youssef ShehabiPlanned ⁦2027-08-08⁩

Post-implementation review

Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?

The review comes after closure

About three months after the forecast finish (⁦2027-07-04⁩), with the sponsor and the benefits owner.

Lessons learned

0 lessons — offered automatically to similar projects when they are created.

Knowledge base

No lessons captured yet

Capture what the team learned during delivery; closure needs at least one.

Benefits handover

Each benefit moves from the project manager to an owner who measures it after closure.

No benefits recorded for this project.