Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection

Sheikh Najjar Industrial City Rehabilitation

Remove from watchlist

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 7.2B

Actual cost

SYP 3.1B

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 8B

+SYP 883.7M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Project documents by stage

What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.

Open in the repository
  • ⁦0⁩ of ⁦7⁩ mandatory documents due
  • 7 mandatory documents missing
  • 1 document in the repository

Documents in the project folder

Archived automatically when the project closes, and kept read-only under the retention policy.

Stages and required documents

For each of the five stages, what its gates and forms require: present, missing, or not yet due.

  1. 1Pre-start
    • Project proposal & feasibility studyMandatory· Missing

      Approval gate G1

    • Priority & weight assessmentOptional· Missing

      Annual work plan

  2. 2Initiation
    • Approved project charterMandatory· Missing

      Initiation gate G2

    • Kick-off meeting minutesMandatory· Missing

      Initiation gate G2

  3. 3Planning
    • Project management plan, schedule & baselineMandatory· Missing

      Planning gate G3

    • Contract or purchase orderMandatory· Missing

      Finance & procurement — when there is a contract

    • Technical studies & drawingsOptional· Present

      Geotechnical survey — damaged plots in Sheikh NajjarV1

      Project management plan

  4. 4ExecutionCurrent stage
    • Periodic update cards & status reportsMandatory· Missing

      Periodic update card form

    • Deliverable completion certificatesMandatory· Missing

      Deliverable completion certificate form

    • Corrective plan when off trackOptional· Missing

      Corrective plan form

  5. 5Closure
    • Project closure & handover formMandatory· Not yet due

      Closure gate G4

    • Lessons learnedMandatory· Not yet due

      Closure gate G4

    • Acceptance test resultsOptional· Not yet due

      Deliverable acceptance

Documents linked to stages and tasks

Each document is tied to its stage of the project lifecycle and to the plan activities it serves — pick an activity to open it on the schedule

Project documents1
Linked to tasks0
Tasks with documents0

Evidence tied to deliverables

Each deliverable with its repository document and the files that prove it.

  • 006-D1Project plan & baselinePRJ-2026-006_1.1_v1.pdfApprovedDeliverable
  • 006-D2Monitoring & reportingPRJ-2026-006_1.2_v1.pdfApprovedDeliverable
  • 006-D3Detailed designPRJ-2026-006_2.1_v1.pdfApprovedDeliverable
  • 006-D4Permits & approvalsPRJ-2026-006_2.2_v1.pdfApprovedDeliverable
  • 006-D5Site works & excavationPRJ-2026-006_3.1_v1.pdfApprovedDeliverable
  • 006-D6StructurePRJ-2026-006_3.2_v1.pdfIn reviewDeliverable
  • 006-D7FinishesNo evidence filed yetDraftDeliverable
  • 006-D8SupplyNo evidence filed yetDraftDeliverable
  • 006-D9InstallationNo evidence filed yetDraftDeliverable
  • 006-D10Testing & commissioningNo evidence filed yetDraftDeliverable
  • 006-D11Provisional acceptanceNo evidence filed yetDraftDeliverable
  • 006-D12Final acceptanceNo evidence filed yetDraftDeliverable
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close