Rising prices of imported equipment and fit-out
PRK-06-1·Transfer·Eng. Youssef Shehabi
Programme · PG-06 · Health, Education & Industrial Recovery Portfolio
The Sheikh Najjar industrial city rehabilitation and the Latakia University technical engineering faculty extension.
incl. SYP 300M programme reserve
46% of budget
Estimate at completion
Planned 53%
Cost performance index 0.92
Manager
Eng. Youssef Shehabi
Senior Project Manager — Governorate Projects
Sponsor
Eng. Bashir Al-Tai
Deputy President, Local Development & Governorates
Projects
2 projects
2024-09-01 — 2027-07-04
At risk 1Off track 1
What the programme must achieve, and the strategic objectives it serves.
Bring factories back into production in the Sheikh Najjar industrial city by rehabilitating its roads and networks
Extend the Latakia University technical engineering faculty to train technicians
Tie technical training to the needs of returning factories
From baseline to target
Teaching space per student
by 2027Industrial plots in operation
by 2027One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
The faculty’s new programmes are built on the needs of factories returning to Sheikh Najjar
Risks that hit more than one project, managed at programme level.
Rising prices of imported equipment and fit-out
PRK-06-1·Transfer·Eng. Youssef Shehabi
3 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 1 · Medium | 1 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 1 · Medium | 0 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Infrastructure projects delivered to plan
73%
+1
Target 85%86%
Schools rehabilitated and equipped (cumulative)
185schools
+20
Target 20093%
Investment attracted to reconstruction projects (cumulative)
26.2SYP bn
+3
Target 32.082%
Staff who completed specialist development programmes
23%
+1
Target 25%92%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely3
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
Weekly · Quorum 4
Members
5 members
As needed · Quorum 3
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Sheikh Najjar Industrial City RehabilitationPRJ-2026-006 | Eng. Youssef Shehabi | 4Execution | Off track | 39% | SYP7.2B | SYP8B+12.4% | 0.78Schedule performance index · 0.78 | 0.89Cost performance index · 0.89 |
| Latakia University Technical Engineering Faculty ExtensionPRJ-2026-019 | Eng. Youssef Shehabi | 4Execution | At risk | 52% | SYP4B | SYP4B+2.0% | 0.93Schedule performance index · 0.93 | 0.98Cost performance index · 0.98 |
| Total · 2 | SYP11.1B | SYP12.1B |
SYP 11.1B
Budget
| Category | Value | Share |
|---|---|---|
| Sheikh Najjar Industrial City Rehabilitation | SYP 7.2B | 64% |
| Latakia University Technical Engineering Faculty Extension | SYP 4B | 36% |
| Total | SYP 11.1B | 100% |