People return to their towns and villages when a hospital works and a school is open; every bed and classroom rehabilitated shows its effect in the governorate directly.
The objective’s weakest KPI, “Hospital beds rehabilitated in public hospitals (cumulative)”, is at 75% of its target, and its heaviest project, “Hama National Hospital Upgrade & Extension”, is Critical. Fixing that one path lifts the objective more than any other action.
This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.
Approved in plan version 1.1Higher Council resolution HCED-2026-032026-03-25
No change requests on this item since the plan was approved.
Corrective actions
What we are doing to bring the KPI back on track, who owns it, and by when.
Hand over the east-wing wards of Hama National Hospital in two batches instead of one
Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014·fadi.aldroubi@psa.gov.syDue 2026-12-10In 43 days2026-12-10K-3.1.1Hama National Hospital Upgrade & Extension
In progress
Challenges & notes
What holds the objective back and what leadership should know.
Challenge
Medical equipment is slow to arrive: three hospitals are below 20% of their fit-out plan.
Eng. Sara Al-Barazi · 2026-10-16
Note
More than 180 schools have been rehabilitated and equipped for the first time this quarter.