PRJ-2026-029On track3PlanningWaterfallNot startedDelivered by:Ministry of Education

e-Learning Platform & Computer Labs for Raqqa Schools

Add to watchlist

Computer labs in 30 schools in Raqqa city and an e-learning platform with the national curriculum, plus teacher training.

Budget (BAC)

SYP 187.5M

Actual cost

SYP 7.5M

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 187.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+6

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦4% done against 4% planned⁩.

⁦SPI 1⁩.⁦00⁩, ⁦CPI 1⁩.⁦00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Human DevelopmentSO-3.1Better access to health and education

Main initiative

SI-4.1.1Rural development & reviving wheat

Contribution to the initiative⁦54%⁩

The project’s share of the initiative’s project budget (2 projects)

Annual work-plan line
WP-2026-029
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦4%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦96%⁩

1 deliverable accepted

  • Project plan & baseline⁦4%⁩

0 deliverables under inspection or acceptance

    Progress & earned value

    ⁦1⁩ of ⁦5⁩ milestones complete

    Earned-value curve

    Planned, earned and actual to the data date, cumulative, with the forecast cost tail

    • Planned value
    • Earned value
    • Actual cost
    • Estimate at completion
    • Budget at completion

    Budget & commitments

    Commitments are ⁦12%⁩ of budget

    SYP7.5M/ SYP187.5M
    Actual spend
    SYP7.5M
    Committed
    SYP22.5M
    Approved budget
    SYP187.5M
    Estimate at completion
    SYP187.5M

    Next milestones

    • Contract signed⁦2026-11-04⁩On track
    • 50% of works complete⁦2027-04-29⁩On track
    • Provisional acceptance⁦2027-11-21⁩On track
    • Closure⁦2027-12-31⁩On track

    Waiting on someone

    ⁦0⁩ approvals and ⁦0⁩ open actions on this project

    Approvals & requests

    From «My actions» for this project

    • No approvals pending

    Actions

    ⁦0⁩ open

    • No actions on this project

    Change requests

    Cost and schedule impact

    • No change requests

    Risks & impediments

    0 open risks, exposure SYP 0

    Risk map

    Probability
    5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
    4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
    3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
    2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
    1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
    12345

    Impact

    • Critical0
    • High0
    • Medium0
    • Low0

    Top risks

    • No open risks

    Open impediments

    ⁦0⁩ escalated

    • No open impediments

    Deliverables

    ⁦1⁩ of ⁦11⁩ approved

    • Project plan & baseline029-D1 · V1 · CRT-029-01⁦4%⁩Mariam Al-Zoubi2026-10-242026-10-24Approved
    • Monitoring & reporting029-D2 · V0⁦4%⁩Eng. Fadi Al-DroubiIn 40 days2026-12-07Draft
    • Business requirements029-D3 · V0⁦9%⁩Eng. Fadi Al-DroubiIn 83 days2027-01-19Draft
    • Solution design029-D4 · V0⁦9%⁩Eng. Abdulrahman Al-KilaniIn 126 days2027-03-03Draft
    • Release 1029-D5 · V0⁦13%⁩Eng. Abdulrahman Al-KilaniIn 169 days2027-04-15Draft
    • Release 2029-D6 · V0⁦13%⁩Mariam Al-ZoubiIn 213 days2027-05-29Draft
    • Integrations029-D7 · V0⁦13%⁩Eng. Fadi Al-DroubiIn 256 days2027-07-11Draft
    • System testing029-D8 · V0⁦10%⁩Mariam Al-ZoubiIn 299 days2027-08-23Draft
    • User acceptance testing029-D9 · V0⁦10%⁩Eng. Fadi Al-DroubiIn 342 days2027-10-05Draft
    • Training & change029-D10 · V0⁦8%⁩Eng. Fadi Al-DroubiIn 386 days2027-11-18Draft
    • Go-live & handover029-D11 · V0⁦7%⁩Eng. Abdulrahman Al-KilaniIn 429 days2027-12-31Draft

    Team, contracts & documents

    Team

    2 members

    Mariam Al-Zoubi · Director, Education & Rural Development ProjectsMuhannad Al-Homsi · Director General, Human Resources & Administrative Development
    • Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsProject managerP-029mariam.alzoubi@psa.gov.sy⁦35%⁩
    • Muhannad Al-HomsiMuhannad Al-HomsiDirector General, Human Resources & Administrative DevelopmentTeacher training tracks on the platformP-019muhannad.alhomsi@psa.gov.sy⁦15%⁩

    Contracts

    0 contracts

    • No external contracts — delivered in-house

    Documents

    • No documents yet

    Meetings

    • No meetings scheduled