A late medium-term plan approval delays the new performance KPIs
PRK-10-1·Accept·Rana Al-Samman
Programme · PG-10 · Planning, Statistics & Capability Portfolio
The medium-term and governorate plans, ministries performance follow-up, the digital crop survey and e-learning in Raqqa.
incl. SYP 37.5M programme reserve
50% of budget
Estimate at completion
Planned 55%
Cost performance index 1.00
Manager
Mariam Al-Zoubi
Director, Education & Rural Development Projects
Sponsor
Dr. Mais Al-Sibai
Director General, Strategy & National Projects
Projects
4 projects
2025-09-07 — 2027-12-31
On track 3At risk 1
What the programme must achieve, and the strategic objectives it serves.
An approved 2026–2028 medium-term plan and governorate plans, turned into portfolios and initiatives
Raise national PMO maturity to 3.5 out of 5
25% of relevant Authority staff through specialist development tracks
From baseline to target
National PMO maturity index
by 2027Employee engagement index
by 2027One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
The national dashboards are built on the new medium-term plan’s KPIs
Wheat-season targets are derived from the farm-sector chapter of the medium-term plan
The farm-survey data picks the rural Raqqa schools to equip first
Risks that hit more than one project, managed at programme level.
A late medium-term plan approval delays the new performance KPIs
PRK-10-1·Accept·Rana Al-Samman
1 risk
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 0 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 1 · Medium | 0 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Statistical bulletins and reports published (cumulative)
8bulletins
+1
Target 1267%
Monthly visits to the national indicators portal
14.1thousand visits
+1
Target 15.094%
Schools rehabilitated and equipped (cumulative)
185schools
+20
Target 20093%
Local projects delivered under governorate plans (cumulative)
610projects
+130
Target 90068%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely4
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Weekly · Quorum 4
Fortnightly · Quorum 4
Members
7 members
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Ministries Performance Follow-up & National DashboardsPRJ-2026-012 | Nizar Abu Fakhr | 4Execution | On track | 76% | SYP245M | SYP245M0.0% | 1.01Schedule performance index · 1.01 | 1.00Cost performance index · 1.00 |
| Hasakah Wheat Digital Crop SurveyPRJ-2026-027 | Mariam Al-Zoubi | 4Execution | At risk | 63% | SYP160M | SYP163.3M+2.0% | 0.88Schedule performance index · 0.88 | 0.98Cost performance index · 0.98 |
| Preparing the 2026–2028 Medium-Term Plan & Governorate PlansPRJ-2026-028 | Rana Al-Samman | 4Execution | On track | 70% | SYP80M | SYP80M0.0% | 1.03Schedule performance index · 1.03 | 1.00Cost performance index · 1.00 |
| e-Learning Platform & Computer Labs for Raqqa SchoolsPRJ-2026-029 | Mariam Al-Zoubi | 3Planning | On track | 4% | SYP187.5M | SYP187.5M0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 |
| Total · 4 | SYP672.5M | SYP675.8M |
SYP 672.5M
Budget
| Category | Value | Share |
|---|---|---|
| Ministries Performance Follow-up & National Dashboards | SYP 245M | 36% |
| Hasakah Wheat Digital Crop Survey | SYP 160M | 24% |
| Preparing the 2026–2028 Medium-Term Plan & Governorate Plans | SYP 80M | 12% |
| e-Learning Platform & Computer Labs for Raqqa Schools | SYP 187.5M | 28% |
| Total | SYP 672.5M | 100% |