PRJ-2026-029On track3PlanningWaterfallNot startedDelivered by:Ministry of Education

e-Learning Platform & Computer Labs for Raqqa Schools

Add to watchlist

Computer labs in 30 schools in Raqqa city and an e-learning platform with the national curriculum, plus teacher training.

Budget (BAC)

SYP 187.5M

Actual cost

SYP 7.5M

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 187.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP181.9M⁦16⁩ elements
Unallocated contingencySYP5.6MSYP 9.4M
Budget at completionSYP187.5MPRJ-2026-029
Weighted progress⁦4%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project529⁦2026-08-16⁩⁦2028-01-27⁩⁦4%⁩181.887.50—
1
Phase142⁦2026-08-16⁩⁦2027-01-05⁩⁦50%⁩14.557.50—
1.1
WBS element71⁦2026-08-16⁩⁦2026-10-26⁩⁦100%⁩7.287.500 / 1
1.2
WBS element69⁦2026-10-28⁩⁦2027-01-05⁩⁦0%⁩7.28—1 / 2
2
Phase112⁦2026-12-10⁩⁦2027-04-01⁩⁦0%⁩30.92——
2.1
WBS element69⁦2026-12-10⁩⁦2027-02-17⁩⁦0%⁩15.46—1 / 1
2.2
WBS element69⁦2027-01-22⁩⁦2027-04-01⁩⁦0%⁩15.46—1 / 2
3
Phase155⁦2027-03-06⁩⁦2027-08-08⁩⁦0%⁩72.75——
3.1
WBS element69⁦2027-03-06⁩⁦2027-05-14⁩⁦0%⁩24.25—1 / 1
3.2
WBS element69⁦2027-04-18⁩⁦2027-06-26⁩⁦0%⁩24.25—1 / 1
3.3
WBS element69⁦2027-05-31⁩⁦2027-08-08⁩⁦0%⁩24.25—1 / 2
4
Phase112⁦2027-07-13⁩⁦2027-11-02⁩⁦0%⁩36.38——
4.1
WBS element69⁦2027-07-13⁩⁦2027-09-20⁩⁦0%⁩18.19—1 / 1
4.2
WBS element69⁦2027-08-25⁩⁦2027-11-02⁩⁦0%⁩18.19—1 / 2
5
Phase112⁦2027-10-07⁩⁦2028-01-27⁩⁦0%⁩27.28——
5.1
WBS element69⁦2027-10-07⁩⁦2027-12-15⁩⁦0%⁩13.64—1 / 1
5.2
WBS element69⁦2027-11-19⁩⁦2028-01-27⁩⁦0%⁩13.64—1 / 1
Total⁦4%⁩181.887.50