e-Learning Platform & Computer Labs for Raqqa Schools
Add to watchlistComputer labs in 30 schools in Raqqa city and an e-learning platform with the national curriculum, plus teacher training.
Budget (BAC)
Actual cost
4% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningStage 3 of 5
Next gate:Execution4 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-12-07 | 2027-01-05 | +29 days | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-03-03 | 2027-04-01 | +29 days | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-07-11 | 2027-08-08 | +28 days | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-10-05 | 2027-11-02 | +28 days | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-12-31 | 2028-01-27 | +27 days | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
4%Awaiting acceptance
0%Not handed in
96%Deliverable flow
Display options
| Project plan & baseline029-D1 | 4% | CRT-029-01 | Approved | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-10-24 | V1 | 3 of 3 |
| Monitoring & reporting029-D2 | 4% | — | Draft | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-12-07 | V0 | 0 of 3 |
| Business requirements029-D3 | 9% | — | Draft | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2027-01-19 | V0 | 0 of 3 |
| Solution design029-D4 | 9% | — | Draft | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2027-03-03 | V0 | 0 of 3 |
| Release 1029-D5 | 13% | — | Draft | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2027-04-15 | V0 | 0 of 3 |
| Release 2029-D6 | 13% | — | Draft | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2027-05-29 | V0 | 0 of 3 |
| Integrations029-D7 | 13% | — | Draft | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2027-07-11 | V0 | 0 of 3 |
| System testing029-D8 | 10% | — | Draft | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2027-08-23 | V0 | 0 of 3 |
| User acceptance testing029-D9 | 10% | — | Draft | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2027-10-05 | V0 | 0 of 3 |
| Training & change029-D10 | 8% | — | Draft | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2027-11-18 | V0 | 0 of 3 |
| Go-live & handover029-D11 | 7% | — | Draft | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2027-12-31 | V0 | 0 of 3 |
| Total · 11 | 100% |