PRJ-2026-029On track3PlanningWaterfallNot startedDelivered by:Ministry of Education

e-Learning Platform & Computer Labs for Raqqa Schools

Add to watchlist

Computer labs in 30 schools in Raqqa city and an e-learning platform with the national curriculum, plus teacher training.

Budget (BAC)

SYP 187.5M

Actual cost

SYP 7.5M

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 187.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 187.5M split into spent, committed and left, with the estimate at completion

EAC SYP 187.5M
Revised request SYP 187.5M
  • Actual spendSYP 7.5M
  • Committed, not spentSYP 15M
  • Allotted, uncommittedSYP 159.4M
  • Contingency availableSYP 5.6M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 187.5M
Original budgetwhen the first baseline was approved
SYP 187.5M
Approved budgetafter approved change requests
SYP 187.5M
Current budgetavailable to spend now
SYP 187.5M
Revised budgetif the pending changes are approved
SYP 187.5M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 22.5M
Contracts0 active contracts
SYP 0
Purchase orders⁦1⁩ order
SYP 22.5M
Remaining budgetapproved less actual
SYP 180M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 7.5M
Accrualswork done, not yet invoiced
SYP 300K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 187.5M
ContingencySYP 3.8M drawn of SYP 9.4M
SYP 5.6M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 187.5M
ApprovedSYP 187.5M
Estimate at completionSYP 187.5M
Approved equals the estimate
The estimate at completion is SYP 0 (⁦0.0%⁩) below the estimate

From proposal DMD-2026-006 in the annual work plan — its estimated cost

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-51029
  • WBS elements⁦5⁩ elements · P-2026-029.01 …
  • Purchase orders⁦1⁩ synced · ⁦0⁩ manual
  • Invoices & certificatesNo certificates
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 3.8M drawn of SYP 9.4M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 3.8M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance14.558.117.5014.66⁦−0.11⁩
2Analysis & design30.922.660.0031.42⁦−0.50⁩
3Build72.756.260.0073.92⁦−1.17⁩
4Testing & acceptance36.383.130.0036.96⁦−0.59⁩
5Launch & handover27.282.350.0027.72⁦−0.44⁩
Unallocated contingency5.630.000.002.81⁦+2.81⁩
Total187.5022.507.50187.50⁦+0.00⁩

Budget split

WBS

SYP 187.5M

Budget

  • Management & governanceSYP 14.6M⁦8%⁩
  • Analysis & designSYP 30.9M⁦16%⁩
  • BuildSYP 72.8M⁦39%⁩
  • Testing & acceptanceSYP 36.4M⁦19%⁩
  • Launch & handoverSYP 27.3M⁦15%⁩
  • Unallocated contingencySYP 5.6M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-08-24⁩+237

SPI(t) ⁦0.68⁩ against the approved finish ⁦2027-12-31⁩

Planned valuePV
SYP 15.5M
The value of the work that should be done by today.
PV
Earned valueEV
SYP 7.5M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 7.5M
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 187.5M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−7.96⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.49
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 187.5M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 180M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 187.5M
  • If the rest goes to planSYP 187.5M
  • At cost and schedule performanceSYP 378.4M
  • The PM’s bottom-up estimateSYP 187.5M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SYP 187.5M

Variance at completion: ⁦+0.00⁩ SYP M