PRJ-2026-019At risk4ExecutionConstructionIn progressDelivered by:Ministry of Higher Education and Scientific Research

Latakia University Technical Engineering Faculty Extension

Add to watchlist

A new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.

Budget (BAC)

SYP 4B

Actual cost

SYP 2.1B

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 4B

+SYP 80.6M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−11

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦52% done against 56% planned⁩.

⁦SPI 0⁩.⁦93⁩, ⁦CPI 0⁩.⁦98⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Human DevelopmentSO-3.1Better access to health and education

Main initiative

SI-1.1.2Industrial recovery & skills

Contribution to the initiative⁦36%⁩

The project’s share of the initiative’s project budget (2 projects)

Annual work-plan line
WP-2025-019
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦52%⁩

Awaiting acceptance ⁦11%⁩

Not handed in ⁦37%⁩

6 deliverables accepted

  • Site works & excavation⁦15%⁩
  • Structure⁦15%⁩
  • Detailed design⁦7%⁩
  • Permits & approvals⁦7%⁩
  • Project plan & baseline⁦4%⁩
  • Monitoring & reporting⁦4%⁩

1 deliverable under inspection or acceptance

  • Finishes⁦11%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦83%⁩ of budget

SYP2.1B/ SYP4BSYP80.6Mprojected overrun(⁦2.0%⁩)
Actual spend
SYP2.1B
Committed
SYP3.3B
Approved budget
SYP4B
Estimate at completion
SYP4B

Next milestones

  • Provisional acceptance⁦2027-01-11⁩was ⁦2027-01-02⁩At risk
  • Closure⁦2027-03-12⁩was ⁦2027-02-28⁩At risk

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SYP 52.5M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0039Late delivery of lab and workshop equipment for the engineering facultyProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦6⁩ of ⁦12⁩ approved

  • Project plan & baseline019-D1 · V1 · CRT-019-01⁦4%⁩Eng. Youssef Shehabi2025-06-152025-06-15Approved
  • Monitoring & reporting019-D2 · V1 · CRT-019-02⁦4%⁩Ibrahim Al-Saeed2025-08-102025-08-10Approved
  • Detailed design019-D3 · V1 · CRT-019-03⁦7%⁩Ibrahim Al-Saeed2025-10-062025-10-06Approved
  • Permits & approvals019-D4 · V1 · CRT-019-04⁦7%⁩Eng. Bashir Al-Tai2025-12-022025-12-02Approved
  • Site works & excavation019-D5 · V1 · CRT-019-05⁦15%⁩Eng. Bashir Al-Tai2026-01-272026-01-27Approved
  • Structure019-D6 · V1 · CRT-019-06⁦15%⁩Eng. Youssef Shehabi2026-03-252026-03-25Approved
  • Finishes019-D7 · V1⁦11%⁩Ibrahim Al-Saeed160 days overdue2026-05-21In review
  • Supply019-D8 · V0⁦9%⁩Eng. Youssef Shehabi104 days overdue2026-07-16Draft
  • Installation019-D9 · V0⁦8%⁩Ibrahim Al-Saeed47 days overdue2026-09-11Draft
  • Testing & commissioning019-D10 · V0⁦8%⁩Eng. Bashir Al-TaiIn 10 days2026-11-07Draft
  • Provisional acceptance019-D11 · V0⁦6%⁩Ibrahim Al-SaeedIn 66 days2027-01-02Draft
  • Final acceptance019-D12 · V0⁦6%⁩Eng. Bashir Al-TaiIn 123 days2027-02-28Draft

Team, contracts & documents

Team

1 member

Eng. Youssef Shehabi · Senior Project Manager — Governorate Projects
  • Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsProject managerP-023youssef.shehabi@psa.gov.sy⁦45%⁩