PRJ-2026-019At risk4ExecutionConstructionIn progressDelivered by:Ministry of Higher Education and Scientific Research
Latakia University Technical Engineering Faculty Extension
Add to watchlistA new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.
Project managerEng. Youssef ShehabiProject sponsorEng. Bashir Al-TaiProgrammeIndustrial Recovery & Skills Programme
Budget (BAC)
SYP 4B
Actual cost
SYP 2.1B
53% of budget
Progress
52%Awaiting acceptance 11%
Estimate at completion
SYP 4B
+SYP 80.6M
SPI · CPI
0.93Schedule performance index · 0.930.98Cost performance index · 0.98
Forecast finish
2027-03-12
12 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure2 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-019-2026-10 | Draft | 52% | — | 2026-10-26 |
| September 2026UPD-019-2026-09 | Approved | 49% | — | 2026-10-02 |
| August 2026UPD-019-2026-08 | Approved | 46% | — | 2026-09-02 |