Latakia University Technical Engineering Faculty Extension
Add to watchlistA new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.
Budget (BAC)
Actual cost
53% of budget
Progress
Estimate at completion
+SYP 80.6M
SPI · CPI
Forecast finish
12 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure2 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started
Closure readiness
Closure planned after the forecast finish on 2027-03-12
A preview of what closure will need, with the planned dates, and the lessons captured so far.
Closure checklist
Seven mandatory items before any project closes.
- 1
Deliverables acceptedNot started
Final acceptance of every deliverable
Ibrahim Al-SaeedPlanned 2027-03-02
- 2
Financial closureNot started
Spend reconciled, commitments closed
Omar Al-NahhasPlanned 2027-04-01
- 3
Contract closureNot started
Contracts closed, bonds released
Omar Al-NahhasPlanned 2027-04-11
- 4
Documents archivedNot started
Documents archived with classification
Eng. Youssef ShehabiPlanned 2027-04-06
- 5
Lessons learnedNot started
Lessons-learned session
Eng. Youssef ShehabiPlanned 2027-03-27
- 6
Benefits owner assignedNot started
Benefits handed to their owner with a measurement plan
Ibrahim Al-SaeedPlanned 2027-03-22
- 7
Final report approvedNot started
Final report and its approval
Eng. Youssef ShehabiPlanned 2027-04-16
Post-implementation review
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
The review comes after closure
About three months after the forecast finish (2027-03-12), with the sponsor and the benefits owner.
Lessons learned
0 lessons — offered automatically to similar projects when they are created.
No lessons captured yet
Capture what the team learned during delivery; closure needs at least one.
Benefits handover
Each benefit moves from the project manager to an owner who measures it after closure.
No benefits recorded for this project.