PRJ-2026-019At risk4ExecutionConstructionIn progressDelivered by:Ministry of Higher Education and Scientific Research

Latakia University Technical Engineering Faculty Extension

Add to watchlist

A new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.

Budget (BAC)

SYP 4B

Actual cost

SYP 2.1B

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 4B

+SYP 80.6M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Latakia University Technical Engineering Faculty Extension

APPROVEDV2Approved ⁦2025-03-14⁩

1Project identity

Required at this stage
Project name
Latakia University Technical Engineering Faculty Extension
Project code
PRJ-2026-019
Project sponsor
Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy
Project manager
Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy
Project owner
Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy
Portfolio & programme
Health, Education & Industrial Recovery PortfolioIndustrial Recovery & Skills Programme
Type & methodology
Construction · Construction
Current phase
4Execution

2Background & rationale

Required at this stage

A new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.

3Objectives

Required at this stage
  1. 1Better access to health and education
  2. 2Develop human capital in public bodies

4Scope

Required at this stage

In scope

  • A new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.
  • Syrian Arab Building Code compliance
  • Consultant-approved drawings

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Syrian Arab Building Code compliance
  2. 2Consultant-approved drawings
  3. 3Health & safety requirements

6Deliverables

Required at this stage
1Project management plan⁦2025-04-14⁩
2Main deliverable — stage 1⁦2026-03-15⁩
3Main deliverable — final stage⁦2026-11-20⁩
4Final report⁦2027-02-28⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-03-14⁩
  2. Contract signed⁦2025-07-08⁩
  3. 50% of works complete⁦2026-03-15⁩
  4. Provisional acceptance⁦2027-01-02⁩
  5. Closure⁦2027-02-28⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩SYP2.8B
  • Supervision & consulting⁦14.0%⁩SYP552.5M
  • Internal team⁦9.0%⁩SYP355M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩SYP197.5M
The delivering body’s investment-plan allocationsTotalSYP4B

9Timeline

Required at this stage
Start
2025-03-1616 March 2025
Baseline finish
2027-02-2828 February 2027
Duration
⁦23⁩ months

10Key risks

Required at this stage
  • MediumLate delivery of lab and workshop equipment for the engineering faculty

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Authority