Initiation
Project charter
Objective, scope, deliverables, roles and budget
- Form no.
- PSA-PMO-F04
- Template edition
- 3.0
- Version
- V2
- Form date
- 2025-03-14
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-019
- Project
- Latakia University Technical Engineering Faculty Extension
- Portfolio
- Health, Education & Industrial Recovery Portfolio
- Sector
- Development Projects Follow-up Sector
- Sponsor
- Eng. Bashir Al-Tai
- Project manager
- Eng. Youssef Shehabi
1Objective
Background
A new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.
Project objectives
- Better access to health and education
- Develop human capital in public bodies
2Scope
In scope
- A new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.
- Syrian Arab Building Code compliance
- Consultant-approved drawings
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
3Deliverables and milestones
| Deliverable | Due |
|---|---|
| Project management plan | 2025-04-14 |
| Main deliverable — stage 1 | 2026-03-15 |
| Main deliverable — final stage | 2026-11-20 |
| Final report | 2027-02-28 |
| Milestone | Date |
|---|---|
| Charter approved | 2025-03-14 |
| Contract signed | 2025-07-08 |
| 50% of works complete | 2026-03-15 |
| Provisional acceptance | 2027-01-02 |
| Closure | 2027-02-28 |
4RolesAuto-filled
- SponsorAuto-filled
- Eng. Bashir Al-Tai
- Project ownerAuto-filled
- Ibrahim Al-Saeed
- Project managerAuto-filled
- Eng. Youssef Shehabi
| Stakeholder | Role |
|---|---|
| Project sponsor | Decisions and funding |
| Project owner | Accepts deliverables, owns benefits |
| National Project Management Office (PMO) | Governance and compliance |
| Governance body | Role | Cadence |
|---|---|---|
| Change Committee | Approves scope, cost and schedule changes | Weekly |
| Project Approval Committee | Methodology compliance, data quality, stage gates | Fortnightly |
| Project management team | Day-to-day control, risks, impediments, the periodic update card | Weekly |
5BudgetAuto-filled
| Line | Amount |
|---|---|
| Main contract | SYP 2.8B |
| Supervision & consulting | SYP 552.5M |
| Internal team | SYP 355M |
| Contingency reserve (5%) | SYP 197.5M |
| Approved budget | SYP 4B |
Funding
The delivering body’s investment-plan allocations
6Success criteria and constraints
Success criteria
- Delivered within the approved budget
- On the approved date ±5%
- Target benefits within 12 months
Constraints
- Stay within the approved budget
- Comply with the unified contracts law (Law 51 of 2004)
Assumptions
- Named internal staff available throughout
- Approvals land within the workflow’s action time limits
Approval logChain: Project charter approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Youssef ShehabiSenior Project Manager — Governorate Projects | Submitted | — | 2025-03-05 10:00 |
| 2 | PMO compliance | Methodology review | Dr. Reem Al-QabbaniPMO — director | Approved | — | 2025-03-08 12:30 |
| 3 | Project owner | Technical acceptance | Ibrahim Al-SaeedProject owner | Approved | — | 2025-03-11 09:45 |
| 4 | Budget funding confirmed | Financial approval | Rasha Al-MudarresFinance | Approved | — | 2025-03-12 11:10 |
| 5 | Sponsor approval | Technical acceptance | Eng. Bashir Al-TaiProject sponsor | Approved | — | 2025-03-14 11:00 |
Signatures
PMO compliance
Dr. Reem Al-Qabbani
Approved2025-03-08
Project owner
Ibrahim Al-Saeed
Approved2025-03-11
Budget funding confirmed
Rasha Al-Mudarres
Approved2025-03-12
Sponsor approval
Eng. Bashir Al-Tai
Approved2025-03-14