PRJ-2026-019At risk4ExecutionConstructionIn progressDelivered by:Ministry of Higher Education and Scientific Research
Latakia University Technical Engineering Faculty Extension
Add to watchlistA new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.
Project managerEng. Youssef ShehabiProject sponsorEng. Bashir Al-TaiProgrammeIndustrial Recovery & Skills Programme
Budget (BAC)
SYP 4B
Actual cost
SYP 2.1B
53% of budget
Progress
52%Awaiting acceptance 11%
Estimate at completion
SYP 4B
+SYP 80.6M
SPI · CPI
0.93Schedule performance index · 0.930.98Cost performance index · 0.98
Forecast finish
2027-03-12
12 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure2 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started