Latakia University Technical Engineering Faculty Extension
Add to watchlistA new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.
Budget (BAC)
Actual cost
53% of budget
Progress
Estimate at completion
+SYP 80.6M
SPI · CPI
Forecast finish
12 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure2 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started
Team & roles
1 member, about 0.5 full-time equivalents
Leadership
1 member
- Eng. Youssef ShehabiProject manager45%A
A AccountableR ResponsibleC ConsultedI Informed
Stakeholders
6 stakeholders, 4 of them below the engagement needed
Power / interest matrix
Pick one to see how they are handled
Keep satisfied1
high power, lower interest
Manage closely4
high power and interest
Monitor0
minimal effort
Keep informed1
high interest, lower power
Interest
Project sponsor
Eng. Bashir Al-Tai
Decisions and funding
Influence
Interest
Engagement level
Unaware
Resistant
Neutral
Supportive
Leading
A gap of 1 step — needs an engagement plan.
- Impact on the project
- Approves gates and changes
- Engagement plan
- Monthly briefing
Display options
| Organisation | Role | Actions | ||||||
|---|---|---|---|---|---|---|---|---|
| Eng. Bashir Al-Tai | Project sponsor | Decisions and funding | SupportiveLeading | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | 2026-10-19 | |||
| Ibrahim Al-Saeed | Project owner | Accepts deliverables, owns benefits | Leading | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | 2026-10-22 | |||
| Project Management Office (PMO) | Governance | Compliance and data quality | Supportive | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | 2026-10-16 | |||
| General Directorate of Financial Affairs | Internal department | Payment approval | NeutralSupportive | Huda Al-DandalHuda Al-DandalSenior Financial Analyst — Investment PlanP-037huda.aldandal@psa.gov.sy | 2026-10-13 | |||
| Al-Sahel Contracting & Development Co. | Main vendor | Delivers the contracted work | NeutralSupportive | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | 2026-10-23 | |||
| End beneficiaries | Beneficiaries | Users of the outcome | NeutralSupportive | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | 2026-09-25 |
Communication plan
Who needs what, when, through which channel, and who owns it.
- Project sponsorStatus and decisions neededMonthlyMeetingEng. Youssef Shehabi2026-11-14
- Project ownerDeliverable status and acceptance datesFortnightlyEmailEng. Youssef Shehabi2026-11-02Overdue
- PMOData and indicator updatesWeeklyDashboardEng. Youssef Shehabi2026-10-30
- BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Youssef ShehabiAt launch
Coming up
By date
- 302026-10PMODashboard · Weekly
- 022026-11Project ownerEmail · Fortnightly
- 142026-11Project sponsorMeeting · Monthly