PRJ-2026-019At risk4ExecutionConstructionIn progressDelivered by:Ministry of Higher Education and Scientific Research

Latakia University Technical Engineering Faculty Extension

Add to watchlist

A new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.

Budget (BAC)

SYP 4B

Actual cost

SYP 2.1B

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 4B

+SYP 80.6M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
PSA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2025-04-10⁩
ApprovedPRJ-2026-019Latakia University Technical Engineering Faculty Extension

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-019
Project
Latakia University Technical Engineering Faculty Extension
Portfolio
Health, Education & Industrial Recovery Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Eng. Bashir Al-Tai
Project manager
Eng. Youssef Shehabi

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-03-16⁩

Baseline finish

⁦2027-02-28⁩

Forecast finish

⁦2027-03-12⁩

SPI

0.93

MilestonePlannedForecastSlip
Project plan approved⁦2025-08-10⁩⁦2025-11-04⁩+86 days
Designs approved⁦2025-12-02⁩⁦2026-05-02⁩+151 days
Build complete⁦2026-05-21⁩⁦2026-11-26⁩+189 days
Testing & acceptance complete⁦2026-11-07⁩⁦2027-01-28⁩+82 days
Final handover⁦2027-02-28⁩⁦2027-03-11⁩+11 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦4%⁩⁦2025-06-15⁩Eng. Youssef Shehabi
Monitoring & reporting⁦4%⁩⁦2025-08-10⁩Ibrahim Al-Saeed
Detailed design⁦7%⁩⁦2025-10-06⁩Ibrahim Al-Saeed
Permits & approvals⁦7%⁩⁦2025-12-02⁩Eng. Bashir Al-Tai
Site works & excavation⁦15%⁩⁦2026-01-27⁩Eng. Bashir Al-Tai
Structure⁦15%⁩⁦2026-03-25⁩Eng. Youssef Shehabi
Finishes⁦11%⁩⁦2026-05-21⁩Ibrahim Al-Saeed
Supply⁦9%⁩⁦2026-07-16⁩Eng. Youssef Shehabi
Installation⁦8%⁩⁦2026-09-11⁩Ibrahim Al-Saeed
Testing & commissioning⁦8%⁩⁦2026-11-07⁩Eng. Bashir Al-Tai
Provisional acceptance⁦6%⁩⁦2027-01-02⁩Ibrahim Al-Saeed
Final acceptance⁦6%⁩⁦2027-02-28⁩Eng. Bashir Al-Tai
Accepted with a certificate⁦52%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0039Late delivery of lab and workshop equipment for the engineering faculty9MitigateEng. Youssef Shehabi

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Youssef Shehabi
Project ownerDeliverable status and acceptance datesFortnightlyEng. Youssef Shehabi
PMOData and indicator updatesWeeklyEng. Youssef Shehabi
BeneficiariesWhat changes and whenAt each milestoneEng. Youssef Shehabi
Team memberRoleAllocation
Eng. Youssef ShehabiProject manager⁦45%⁩

5QualityAuto-filled

Quality leadAuto-filled
Eng. Youssef Shehabi
Review cadenceAuto-filled
A monthly quality walk; acceptance per floor
Next reviewAuto-filled
⁦2026-11-18⁩
Quality criterionThresholdNowMet
Finishes match the approved samples100%100% after replacementYes
Pump efficiency against design85% or more91%Yes

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Youssef ShehabiSenior Project Manager — Governorate ProjectsSubmitted—⁦2025-04-10⁩ 14:29
2Methodology review — PMOMethodology reviewMariam Al-ZoubiPMO — analystApprovedComplete against the project management plan template.⁦2025-04-14⁩ 10:31
3Technical acceptance — project ownerTechnical acceptanceIbrahim Al-SaeedProject ownerApproved—⁦2025-04-17⁩ 11:38
4Cash flow & financial commitmentFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-04-20⁩ 09:24
5Plan aligned with the contractsFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2025-04-22⁩ 10:01
6Sponsor approvalTechnical acceptanceEng. Bashir Al-TaiProject sponsorApproved—⁦2025-04-27⁩ 14:59

Signatures

Methodology review — PMO

Mariam Al-Zoubi

Approved⁦2025-04-14⁩

Technical acceptance — project owner

Ibrahim Al-Saeed

Approved⁦2025-04-17⁩

Cash flow & financial commitment

Rasha Al-Mudarres

Approved⁦2025-04-20⁩

Plan aligned with the contracts

Abdullah Al-Ujaili

Approved⁦2025-04-22⁩

Sponsor approval

Eng. Bashir Al-Tai

Approved⁦2025-04-27⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Youssef Shehabi on ⁦2025-04-10⁩

  1. Methodology review

    Methodology review — PMO

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-04-14⁩ at ⁦10:31⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Ibrahim Al-Saeed · Project owner

    Approved · ⁦2025-04-17⁩ at ⁦11:38⁩

  3. Financial approval

    Cash flow & financial commitment

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-04-20⁩ at ⁦09:24⁩

  4. Financial approval

    Plan aligned with the contracts

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-04-22⁩ at ⁦10:01⁩

  5. Technical acceptance

    Sponsor approval

    Eng. Bashir Al-Tai · Project sponsor

    Approved · ⁦2025-04-27⁩ at ⁦14:59⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-04-10⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Youssef Shehabi

  2. V1Returned for edit⁦2025-03-27⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Youssef Shehabi