RSK-0039Latakia University Technical Engineering Faculty Extension

Late delivery of lab and workshop equipment for the engineering faculty

9MediumOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

The engineering lab and workshop equipment is imported to a special spec and waits on the standard lab design

Preventive controls

  • An early purchase order for the long-lead equipment
  • Approve the standard lab design from the Aleppo University trial without waiting for it to finish

2 / 2

Event

Late delivery of lab and workshop equipment for the engineering faculty

9MediumTrigger

No purchase order by mid-November

Contingency

Fit two labs with mobile kits until the equipment arrives

Impact

The faculty opens without ready labs; practical training starts a full semester late

SYP 52.5M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
9Medium

Residual

5
4
3
2
1
1
2
3
4
5
6Low

Exposure

SYP 52.5M

Residual

⁦33⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 4 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Youssef Shehabi

    Currently followed up here
  2. 2

    Programme manager

    Eng. Youssef Shehabi

  3. 3

    PMO director

    Dr. Reem Al-Qabbani

  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • An early purchase order for the long-lead equipment

    Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy
    In progressIn 18 days2026-11-15
  • Approve the standard lab design from the Aleppo University trial without waiting for it to finish

    Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy
    Not startedIn 34 days2026-12-01

Trigger

No purchase order by mid-November

Contingency

Fit two labs with mobile kits until the equipment arrives

Esc