Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-019At risk4ExecutionConstructionIn progressDelivered by:Ministry of Higher Education and Scientific Research

Latakia University Technical Engineering Faculty Extension

Add to watchlist

A new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.

Budget (BAC)

SYP 4B

Actual cost

SYP 2.1B

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 4B

+SYP 80.6M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Periodic update — September 2026

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Periodic update card

Progress, status, risks and support requested

Form no.
PSA-PMO-F07
Template edition
2.2
Version
V1
Form date
⁦2026-10-02⁩
ApprovedUPD-019-2026-09Periodic update — September 2026

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-019
Project
Latakia University Technical Engineering Faculty Extension
Portfolio
Health, Education & Industrial Recovery Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Eng. Bashir Al-Tai
Project manager
Eng. Youssef Shehabi

1ProgressAuto-filled

From the live data: accepted deliverables, the schedule and finance on the period’s last day.

Actual progress

⁦49%⁩

+3 pts on the last period

Planned to date

⁦53%⁩

SPI

0.94

Actual cost

SYP 2B

Main achievements this periodFilled by the project manager

Work went to the approved plan for the period, with the due deliverables handed in.

Prefilled from the August 2026 card — edit it if it changed

2Status

Overall healthAuto-filled
At risk
StageAuto-filled
Execution
Forecast finishAuto-filled
⁦2027-03-12⁩

The PM’s comment on the statusFilled by the project manager

The variance from the baseline stands because of late integrations; the corrective plan is running and followed weekly.

Prefilled from the August 2026 card — edit it if it changed

3Risks and impedimentsAuto-filled

CodeRiskScoreOwner
RSK-0039Late delivery of lab and workshop equipment for the engineering faculty9Eng. Youssef Shehabi
CodeImpedimentSeverity
No open impediments

4Support requested

What the project needs from leadership or the committeesFilled by the project manager

Approve change request CR-2026-012 for three integration engineers (SYP 24.5M), and the President of the Authority to press the Ministry of Interior on the civil-registry test environment.

Prefilled from the August 2026 card — edit it if it changed

Includes financial supportAuto-filled
Yes

Approval logChain: Periodic update approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Youssef ShehabiSenior Project Manager — Governorate ProjectsSubmitted—⁦2026-10-02⁩ 09:12
2PMO checkMethodology reviewMariam Al-ZoubiPMO — analystApprovedThe reading agrees with the schedule and finance.⁦2026-10-04⁩ 09:00
3Sponsor review & approvalTechnical acceptanceEng. Bashir Al-TaiProject sponsorApproved—⁦2026-10-06⁩ 10:07

Signatures

PMO check

Mariam Al-Zoubi

Approved⁦2026-10-04⁩

Sponsor review & approval

Eng. Bashir Al-Tai

Approved⁦2026-10-06⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F07 · version V1

Periodic update card

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Periodic update approval · version ⁦1⁩

Submitted by Eng. Youssef Shehabi on ⁦2026-10-02⁩

  1. Methodology review

    PMO check

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-10-04⁩ at ⁦09:00⁩

    The reading agrees with the schedule and finance.

  2. Technical acceptance

    Sponsor review & approval

    Eng. Bashir Al-Tai · Project sponsor

    Approved · ⁦2026-10-06⁩ at ⁦10:07⁩

Steps that do not apply to this record

  • Financial support requested — the condition «Financial link?» does not hold

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-10-02⁩

    The card as the PM filled it

    • Prefilled from the previous period’s card and the live data

    Eng. Youssef Shehabi

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close