Project status card
28 October 2026
Latakia University Technical Engineering Faculty Extension
PRJ-2026-019 · Development Projects Follow-up Sector · Strategic · WP-2025-019
- Progress
- 52% / 56%
- SPI · CPI
- 0.93 · 0.98
- Spend
- SYP 2.1B / SYP 4B
- Estimate at completion
- SYP 4B
Schedule
Planned to date 56%
Forecast finish: 2027-03-12 · 12 days late
SPI0.93Schedule performance index · 0.93CPI0.98Cost performance index · 0.98Health dimensions
Last update: 2026-10-25 · Up to date
Deliverables
6 of 9 due deliverables accepted on time (67%)
Next milestones
- Build complete2026-11-26
- Testing & acceptance complete2027-01-28
- Final handover2027-03-11
Top risks
- Late delivery of lab and workshop equipment for the engineering faculty9
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SYP 3.95bn: 0 on track and 0 red or critical. Weighted progress is 52% against 56% planned, spend SYP 2.1bn, and EAC SYP 4.03bn (SYP 80.6M over).
No project is more than a month behind baseline.