Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-019At risk4ExecutionConstructionIn progressDelivered by:Ministry of Higher Education and Scientific Research

Latakia University Technical Engineering Faculty Extension

Add to watchlist

A new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.

Budget (BAC)

SYP 4B

Actual cost

SYP 2.1B

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 4B

+SYP 80.6M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

Latakia University Technical Engineering Faculty Extension

PRJ-2026-019 · Development Projects Follow-up Sector · Strategic · WP-2025-019

In progressAt risk4ExecutionProject manager: Eng. Youssef Shehabi · Sponsor: Eng. Bashir Al-Tai
Progress
⁦52%⁩ / ⁦56%⁩
SPI · CPI
0.93 · 0.98
Spend
SYP 2.1B / SYP 4B
Estimate at completion
SYP 4B

Schedule

⁦4%⁩ behind⁦52%⁩

Planned to date ⁦56%⁩

Forecast finish: 2027-03-12 · 12 days late

SPI0.93Schedule performance index · 0.93CPI0.98Cost performance index · 0.98

Health dimensions

At risk

Last update: 2026-10-25 · Up to date

Deliverables

⁦6⁩ of ⁦9⁩ due deliverables accepted on time (⁦67%⁩)

Next milestones

  • Build complete2026-11-26
  • Testing & acceptance complete2027-01-28
  • Final handover2027-03-11

Top risks

  • Late delivery of lab and workshop equipment for the engineering faculty9

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SYP 3.95bn: 0 on track and 0 red or critical. Weighted progress is 52% against 56% planned, spend SYP 2.1bn, and EAC SYP 4.03bn (SYP 80.6M over).

No project is more than a month behind baseline.

Planning and Statistics Authority · prepared by Eng. Youssef Shehabi in MunjazInternal

Status: At risk ·Project page