Unified e-services platform status card
Unified Government e-Services Platform · Week 43 — to 27 October 2026
Shown by your permissionsProject Management Office: 1 project — everything in your scope
Project status card
Unified e-services platform status card
Unified Government e-Services Platform
- Period
- Week 43 — to 27 October 2026
- Generated
- 27 October 2026
- Submitted to
- The sponsor, the project owner and the PMO
- Owner
- Eng. Tarek Al-Mardini
Prepared by the National PMO — automatically, on Munjaz
Executive summary
Written by Copilot from system data — review before sending
The project is 58% complete against 67% planned (SPI 0.87) and is forecast to finish on 12 May 2027 instead of 31 March 2027 — 42 days late. The slip sits in national-systems and ministry integration (41% done) and the “Wave 1 complete” milestone, which missed 30 September and is now forecast for 12 November.
Three main causes: (1) the shared civil-registry test environment was down for 9 days; (2) two vendor integration engineers left with no replacement — an impediment now overdue; (3) internal resource strain — the lead integration engineer is at 135% and shared with the mobile app. The request-data migration plan was also returned for rework.
Cost is less affected: CPI 0.96 and EAC SYP 2.25bn against SYP 2.16bn (+4.2%). But the change request to add civil-record transfer & record merge would add another 21 days if approved as submitted.
Key figures
- Projects
- 1
- Budget
- SYP 2.2B
- Spent
- SYP 1.3B
- EAC
- SYP 2.3B
- Progress
- 58% / 67%
- SPI
- 0.87
- CPI
- 0.96
- High risks
- 2
Project health mix
- At risk 1
Earned value
- Planned value
- Earned value
- Actual cost
- Estimate at completion
- Budget at completion
| Period | Planned value | Earned value | Actual cost | Estimate at completion |
|---|---|---|---|---|
| 25-01 | SYP 21.6M | SYP 21.6M | SYP 21.6M | — |
| 25-02 | SYP 43.2M | SYP 43.2M | SYP 43.3M | — |
| 25-03 | SYP 86.4M | SYP 86.4M | SYP 86.7M | — |
| 25-04 | SYP 129.6M | SYP 129.6M | SYP 130.4M | — |
| 25-05 | SYP 183.6M | SYP 183.6M | SYP 185M | — |
| 25-06 | SYP 237.6M | SYP 233.3M | SYP 235.5M | — |
| 25-07 | SYP 302.4M | SYP 293.8M | SYP 297.2M | — |
| 25-08 | SYP 367.2M | SYP 354.3M | SYP 359M | — |
| 25-09 | SYP 432M | SYP 414.7M | SYP 421.2M | — |
| 25-10 | SYP 507.6M | SYP 481.7M | SYP 490.1M | — |
| 25-11 | SYP 583.2M | SYP 550.8M | SYP 561.5M | — |
| 25-12 | SYP 658.8M | SYP 617.8M | SYP 631M | — |
| 26-01 | SYP 734.4M | SYP 682.6M | SYP 698.5M | — |
| 26-02 | SYP 810M | SYP 747.4M | SYP 766.3M | — |
| 26-03 | SYP 885.6M | SYP 812.2M | SYP 834.4M | — |
| 26-04 | SYP 961.2M | SYP 872.7M | SYP 898.3M | — |
| 26-05 | SYP 1B | SYP 933.1M | SYP 962.5M | — |
| 26-06 | SYP 1.1B | SYP 993.6M | SYP 1B | — |
| 26-07 | SYP 1.2B | SYP 1.1B | SYP 1.1B | — |
| 26-08 | SYP 1.3B | SYP 1.1B | SYP 1.2B | — |
| 26-09 | SYP 1.4B | SYP 1.2B | SYP 1.2B | — |
| 26-10 | SYP 1.4B | SYP 1.3B | SYP 1.3B | SYP 1.3B |
| 26-11 | SYP 1.6B | — | — | SYP 1.1B |
| 26-12 | SYP 1.7B | — | — | SYP 918.4M |
| 27-01 | SYP 1.8B | — | — | SYP 679.1M |
| 27-02 | SYP 2B | — | — | SYP 384.5M |
| 27-03 | SYP 2.2B | — | — | SYP 90M |
| 27-04 | SYP 2.2B | — | — | SYP 90M |
| 27-05 | SYP 2.2B | — | — | SYP 90M |
Milestones
| Internal pilot (MVP) live | 2026-03-31 | 2026-04-28 |
| Data classification approved under the data-protection policy | 2026-06-30 | 2026-07-14 |
| Wave 1 development complete (24 services) | 2026-09-30 | 2026-11-12 |
| Civil registry & national interoperability integration complete | 2026-10-31 | 2026-12-10 |
| Penetration test passed, security sign-off | 2026-12-15 | 2027-01-28 |
| User acceptance testing complete | 2027-01-31 | 2027-03-14 |
| Official launch of the unified government e-services platform | 2027-03-01 | 2027-04-15 |
| Final acceptance & final payment | 2027-03-31 | 2027-05-12 |
Projects with the most at stake
| Project | Budget | Progress | Slip | Health |
|---|---|---|---|---|
| Unified Government e-Services Platform | SYP 2.2B | 58% | 42 days | At risk |
Highest-exposure risks
| Risk | Score | Exposure |
|---|---|---|
| Civil-registry identity and interoperability interfaces not ready on timeUnified Government e-Services Platform | 16 | SYP 60M |
| Shortage of integration and back-end engineers on the vendor teamUnified Government e-Services Platform | 16 | SYP 46.3M |
| Late sign-off of service requirements by the owning ministriesUnified Government e-Services Platform | 12 | SYP 30M |
| Possible critical findings in the pre-launch penetration testUnified Government e-Services Platform | 12 | SYP 15M |
| Incomplete migration of open-request data from the ministries’ current systemsUnified Government e-Services Platform | 9 | SYP 18.8M |
| Mobile-app team competing with the platform for the same peopleUnified Government e-Services Platform | 9 | SYP 13M |
| Citizen service centre staff resisting the new digital proceduresUnified Government e-Services Platform | 9 | SYP 7.5M |
Decisions needed
- 1
Approve the updated corrective plan for the Unified Government e-Services Platform
The National Steering Committee recommends conditional approval with a monthly progress review.
- 2
Approve the October National Steering Committee minutes
Reviewed by the committee secretary; no open comments.