SO-3.1 · Better access to health and education

Public hospitals rehabilitation

CriticalDelivered wholly through projectsHuman Development

Upgrading and extending Hama National Hospital with 42 wards, ending nine temporary wards and lifting bed capacity in the central region.

⁦57%⁩

Initiative weighted progress

⁦57.0%⁩

Σ each project’s contribution × its actual progress, over the shares that count

Linked projects’ progress

⁦57.0%⁩

Σ contribution × progress, projects only

Contributions assigned

⁦100%⁩

Complete and approved

Primary projects’ budget

SYP16B

1 primary project

Linked projects and their contributions

Strategy management approves each share; every change is kept in the initiative’s history

ProjectLinkContributionActual progressContribution × progress
Hama National Hospital Upgrade & Extension

PRJ-2026-007

Primary⁦100%⁩⁦57%⁩⁦57.0%⁩

Linked projects’ progress

Σ (contribution × progress) = ⁦57.0%⁩ points ÷ shares counted ⁦100%⁩ = ⁦57.0%⁩

Initiative progress

The initiative runs wholly through its projects, so its progress is theirs: ⁦57.0%⁩

Scope, outputs & phases

As approved with the initiative: what is in scope, what it delivers, and its delivery phases on the timeline.

Scope

Upgrading and extending Hama National Hospital with 42 wards and operating theatres, equipping it and moving patients from the temporary wards.

Outputs

  • A hospital with 42 rehabilitated wards
  • Nine temporary wards closed
  • A maintenance and operation contract for the medical equipment

Delivery phases

  • Construction and extension

    2024-02-04 — 2027-06-01

  • Fit-out and move

    2027-03-01 — 2027-06-30

Today · 2026-10-28

Impact KPIs & benefits

Measured apart from delivery progress: an initiative can be well advanced with no impact yet, and the other way round

Impact KPIs

The strategic KPIs the initiative moves

Benefits

Benefits registered for its projects, planned vs realised

No benefits registered for these projects yet; they are recorded at closure and handover.

These KPIs and benefits do not enter the weighted progress above, and progress does not enter them.

Three separate measures

An example from this initiative: Hama National Hospital Upgrade & Extension

1Deliverable weight in the project

⁦38.0%⁩

Weight of «Civil works» among its deliverables

Deliverable weights add up to 100% inside the project; it progresses as they are accepted.

See where it comes from

2Project weight in the portfolio

⁦27.3%⁩

Its relative weight in Health, Education & Industrial Recovery Portfolio

Set by the project weight model; it feeds portfolio progress: relative weight × actual progress.

See where it comes from

3Contribution to the initiative

⁦100%⁩

Its contribution to «Public hospitals rehabilitation»

Approved by strategy management; it feeds this initiative’s progress only.

Each is set in its own place and moves neither of the others: changing a deliverable’s weight touches neither the project’s portfolio weight nor its contribution.

Risks, obstacles & deviations

The initiative’s own risks and obstacles, the highest open risks of its projects, and the budget and schedule deviation.

  • Obstacle in the wayHighBeing treated

    Contractor claims and five months’ delay on MEP works

    Response: A dispute committee and an approved corrective plan

    Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy

Deviation

Budget: projects total SYP 16B against the estimate SYP 15B

Schedule: last project ends ⁦2027-06-01⁩ against the initiative end ⁦2027-06-30⁩

Approval & change log

This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.

Approved in plan version ⁦1.1⁩Higher Council resolution HCED-2026-032026-03-25

No change requests on this item since the plan was approved.