PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection

Sheikh Najjar Industrial City Rehabilitation

Remove from watchlist

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 7.2B

Actual cost

SYP 3.1B

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 8B

+SYP 883.7M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Sheikh Najjar Industrial City Rehabilitation

APPROVEDV2Approved ⁦2024-08-30⁩

1Project identity

Required at this stage
Project name
Sheikh Najjar Industrial City Rehabilitation
Project code
PRJ-2026-006
Project sponsor
Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy
Project manager
Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy
Project owner
Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy
Portfolio & programme
Health, Education & Industrial Recovery PortfolioIndustrial Recovery & Skills Programme
Type & methodology
Construction · Construction
Current phase
4Execution

2Background & rationale

Required at this stage

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

3Objectives

Required at this stage
  1. 1Stimulate growth, restore production and attract investment
  2. 2Rehabilitate core energy, water and transport infrastructure

4Scope

Required at this stage

In scope

  • Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.
  • Syrian Arab Building Code compliance
  • Consultant-approved drawings

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Syrian Arab Building Code compliance
  2. 2Consultant-approved drawings
  3. 3Health & safety requirements

6Deliverables

Required at this stage
1Project management plan⁦2024-10-09⁩
2Main deliverable — stage 1⁦2025-12-25⁩
3Main deliverable — final stage⁦2026-11-19⁩
4Final report⁦2027-03-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2024-08-30⁩
  2. Contract signed⁦2025-01-30⁩
  3. 50% of works complete⁦2025-12-25⁩
  4. Provisional acceptance⁦2027-01-15⁩
  5. Closure⁦2027-03-31⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩SYP5.1B
  • Supervision & consulting⁦14.0%⁩SYP1B
  • Internal team⁦9.0%⁩SYP642.5M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩SYP357.5M
The delivering body’s investment-plan allocationsTotalSYP7.2B

9Timeline

Required at this stage
Start
2024-09-011 September 2024
Baseline finish
2027-03-3131 March 2027
Duration
⁦31⁩ months

10Key risks

Required at this stage
  • HighGround-improvement costs up after the geotechnical survey
  • MediumLate works approvals from Aleppo Governorate

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Authority