PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection

Sheikh Najjar Industrial City Rehabilitation

Remove from watchlist

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 7.2B

Actual cost

SYP 3.1B

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 8B

+SYP 883.7M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Team & roles

2 members, about ⁦0.8⁩ full-time equivalents

Leadership

2 members

  • Eng. Youssef ShehabiProject manager⁦55%⁩A
  • Eng. Fadi Al-DroubiHuman-development lead on industrial workforce programmes⁦25%⁩Allocated ⁦110%⁩ across all projectsR

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦6⁩ stakeholders, ⁦4⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied1

high power, lower interest

Manage closely4

high power and interest

Monitor0

minimal effort

Keep informed1

high interest, lower power

Eng. Bashir Al-TaiManage closelyEng. Wassim Al-AzmManage closelyProject Management Office (PMO)Manage closelyEnd beneficiariesKeep informedGeneral Directorate of Financial AffairsKeep satisfiedDar Al-Khibra Engineering ConsultantsManage closely

Interest

Project sponsor

Eng. Bashir Al-Tai

Decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Now

Supportive

Target

Leading

A gap of ⁦1⁩ step — needs an engagement plan.

Impact on the project
Approves gates and changes
Engagement plan
Monthly briefing
Last contact⁦2026-10-17⁩
⁦6⁩ results
Export CSV
OrganisationRoleActions
Eng. Bashir Al-TaiProject sponsorDecisions and fundingSupportiveLeadingEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy⁦2026-10-17⁩
Eng. Wassim Al-AzmProject ownerAccepts deliverables, owns benefitsResistantLeadingEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy⁦2026-10-20⁩
Project Management Office (PMO)GovernanceCompliance and data qualitySupportiveEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy⁦2026-10-14⁩
General Directorate of Financial AffairsInternal departmentPayment approvalNeutralSupportiveHuda Al-DandalHuda Al-DandalSenior Financial Analyst — Investment PlanP-037huda.aldandal@psa.gov.sy⁦2026-10-11⁩
Dar Al-Khibra Engineering ConsultantsMain vendorDelivers the contracted workSupportiveEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy⁦2026-10-21⁩
End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy⁦2026-09-23⁩
⁦1⁩–⁦6⁩ of ⁦6⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Project sponsorStatus and decisions neededMonthlyMeetingEng. Youssef Shehabi⁦2026-11-12⁩
  • Project ownerDeliverable status and acceptance datesFortnightlyEmailEng. Youssef Shehabi⁦2026-10-31⁩
  • PMOData and indicator updatesWeeklyDashboardEng. Youssef Shehabi⁦2026-10-28⁩
  • BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Youssef ShehabiAt launch

Coming up

By date

  1. 282026-10PMODashboard · Weekly
  2. 312026-10Project ownerEmail · Fortnightly
  3. 122026-11Project sponsorMeeting · Monthly