PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection

Sheikh Najjar Industrial City Rehabilitation

Remove from watchlist

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 7.2B

Actual cost

SYP 3.1B

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 8B

+SYP 883.7M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−21

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦84%⁩ chance of a further slip within ⁦45⁩ days

From the SPI trend (⁦0.78⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦39% done against 50% planned⁩.

⁦SPI 0⁩.⁦78⁩, ⁦CPI 0⁩.⁦89⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Economic Recovery & Monetary StabilitySO-1.1Stimulate growth, restore production and attract investment

Main initiative

SI-1.1.2Industrial recovery & skills

Contribution to the initiative⁦64%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

Annual work-plan line
WP-2024-006
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦39%⁩

Awaiting acceptance ⁦11%⁩

Not handed in ⁦50%⁩

5 deliverables accepted

  • Site works & excavation⁦16%⁩
  • Detailed design⁦8%⁩
  • Permits & approvals⁦7%⁩
  • Project plan & baseline⁦4%⁩
  • Monitoring & reporting⁦4%⁩

1 deliverable under inspection or acceptance

  • Structure⁦11%⁩

Corrective plan requiredThe project is seriously late (95 days late · SPI ⁦0.78⁩) and has no corrective plan yet.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦89%⁩ of budget

SYP3.1B/ SYP7.2BSYP883.7Mprojected overrun(⁦12.4%⁩)
Actual spend
SYP3.1B
Committed
SYP6.4B
Approved budget
SYP7.2B
Estimate at completion
SYP8B

Next milestones

  • Provisional acceptance⁦2027-03-27⁩was ⁦2027-01-15⁩Late
  • Closure⁦2027-07-04⁩was ⁦2027-03-31⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦1⁩ open action on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦1⁩ open

  • Follow up works approvals with Aleppo GovernorateEng. Youssef ShehabiIn 6 days2026-11-03High

Risks & impediments

2 open risks, exposure SYP 712.5M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩1Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩RSK-0025Late works approvals from Aleppo Governorate1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0024Ground-improvement costs up after the geotechnical surveyProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High1
  • Medium1
  • Low0

Deliverables

⁦5⁩ of ⁦12⁩ approved

  • Project plan & baseline006-D1 · V1 · CRT-006-01⁦4%⁩Eng. Youssef Shehabi2024-12-292024-12-29Approved
  • Monitoring & reporting006-D2 · V1 · CRT-006-02⁦4%⁩Eng. Wassim Al-Azm2025-03-142025-03-14Approved
  • Detailed design006-D3 · V1 · CRT-006-03⁦8%⁩Eng. Wassim Al-Azm2025-05-282025-05-28Approved
  • Permits & approvals006-D4 · V1 · CRT-006-04⁦7%⁩Eng. Bashir Al-Tai2025-08-112025-08-11Approved
  • Site works & excavation006-D5 · V1 · CRT-006-05⁦16%⁩Eng. Bashir Al-Tai2025-10-242025-10-24Approved
  • Structure006-D6 · V1⁦11%⁩Eng. Youssef Shehabi294 days overdue2026-01-07In review
  • Finishes006-D7 · V0⁦11%⁩Eng. Wassim Al-Azm219 days overdue2026-03-23Draft
  • Supply006-D8 · V0⁦9%⁩Eng. Youssef Shehabi145 days overdue2026-06-05Draft
  • Installation006-D9 · V0⁦9%⁩Eng. Wassim Al-Azm70 days overdue2026-08-19Draft
  • Testing & commissioning006-D10 · V0⁦9%⁩Eng. Bashir Al-TaiIn 5 days2026-11-02Draft
  • Provisional acceptance006-D11 · V0⁦6%⁩Eng. Wassim Al-AzmIn 79 days2027-01-15Draft
  • Final acceptance006-D12 · V0⁦6%⁩Eng. Bashir Al-TaiIn 154 days2027-03-31Draft

Team, contracts & documents

Team

2 members

Eng. Youssef Shehabi · Senior Project Manager — Governorate ProjectsEng. Fadi Al-Droubi · Director General, Human Development Projects
  • Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsProject managerP-023youssef.shehabi@psa.gov.sy⁦55%⁩